Use AI to summarize supplier delivery performance by matching comparable purchase-order lines and measuring the same start and end events. Keep the original promise, accepted revised schedule and actual usable receipt distinct. A small history can inform a planning question, but it cannot establish a strong delivery guarantee.
Compare identical part revision, site, process, lot scope and calendar. Define when the clock starts and ends before calculating. The purchase-order history guide explains the difference between order, shipment, dock and usable-receipt dates.
Measure two comparable fictional orders
These records are a separate fictional sample for BRK-140 Rev D at US-NPI-01. Both use the same supplier, route, 20-piece lot and receiving process. Count Monday–Friday business days, excluding the PO issue date and including the date all 20 passed QA and were put away. The calendar has no closures in these intervals.
| PO line | Issued | All units accepted and usable | Elapsed |
|---|---|---|---|
| H-01 | 4 January 2027 | 12 January 2027 | 6 business days |
| H-02 | 11 January 2027 | 21 January 2027 | 8 business days |
The observed range is six to eight business days; the arithmetic mean is seven. With only two lines, neither a 95th percentile nor a reliable on-time probability follows. A planner might select eight days as a provisional assumption and record why, then request a current quantity-specific commitment. The eight-day interval already ends at usable stock, so do not add inspection a second time.
Measure against the right promise
Retain the original agreed date and each buyer-accepted revision. A supplier proposal is a proposed change until the buyer approves it. Measure performance against the original commitment and, separately, against the accepted revised schedule. Count each PO line once for a full-line measure and retain partial receipts under that line. Do not treat a dock scan or an uninspected shipment as usable stock.
| Field | Evidence to retain | Review |
|---|---|---|
| Comparable scope | Supplier, part/revision, site, quantity, process and calendar | Exclude mismatched lines or explain the difference |
| Clock | Issue, promised dock, actual dock and accepted/usable dates | Keep endpoints and units explicit |
| Commitment | Original promise, proposals and accepted schedule | Show both original and latest basis |
| Result | Completed lines, range and missing dates | State sample size and avoid unsupported tail claims |
| Next action | Planning assumption, buyer follow-up and review date | Request a current quantity-specific date |
Arc can match supplier replies to PO lines and compare current commitments with the original order and assembly date. It can flag shifts in supplier delivery performance so the buyer can investigate and prepare a negotiation brief. Receipt acceptance and the selected planning assumption remain with the responsible team.
Frequently asked questions
Can two orders establish a reliable 95th-percentile lead time?
No. Two comparable observations describe only those completed lines. Keep the sample count and range visible, choose a cautious planning assumption and obtain a current commitment for the order.
Should I measure to shipment, dock or usable stock?
Choose the endpoint that answers the decision. A build needs usable material, so include receiving and inspection once; retain separate shipment and dock dates to diagnose where time was spent.
Does a historical average replace a supplier promise?
No. Use history to prepare a question or planning assumption. The current quantity-specific supplier commitment and buyer-accepted schedule determine the order’s recorded date.