Audit your first ten purchase orders by tracing a consecutive sample from the request received by purchasing to the initial PO released to the supplier. Retain timestamps, approval evidence, corrections and the next handoff for each order. Use the longest recurring delay to choose one change and name the person who will test it.
Choose the question before extracting records. This guide measures the internal path to initial issue. It does not score supplier delivery or estimate how quickly parts become usable. Those later decisions belong in the supplier scorecard and PO lead-time history.
Fix the sample and clock before reviewing it
Select ten consecutive initial goods POs from one defined site and release period. Keep repeats, missing evidence and awkward orders. Record the selection date, scope and any exclusions such as service orders or change orders. A convenient selection of fast orders cannot answer how the process normally behaves.
APQC’s requisition-to-PO cycle-time definition measures elapsed days including weekends, from requisition receipt to release of the PO to the supplier, and excludes change orders. Its metric uses an average. This guide uses the same clearly stated endpoints for a local audit but reports both its own median and mean. No external benchmark is used as a target.
The teaching audit freezes ten consecutive initial orders A01–A10 released November 3–14, 2026, at fictional US site AUS-01. The review snapshot is November 16 at noon CST. These are independent invented audit records, not the historical lead-time orders or R-P26’s later bracket PO. All timestamps below are in CST and include nights and weekends. Electronic submissions and approvals can occur outside staffed hours in this fixture. No time is subtracted for office closure.
Copy a source-linked order audit ledger
| Field | Source to retain | What to inspect |
|---|---|---|
| PO ID, version and requisition lines | Initial issued order and contributing internal requests | Which event is in the sample? |
| Request received timestamp | Purchasing intake record | Start of this cycle, even if incomplete |
| Request complete timestamp | Accepted package and clarification history | When did required identity, quantity and documents become reviewable? |
| Final required approval timestamp | Approval record for the relevant version | When could the buyer proceed under the stated authority? |
| PO released to supplier timestamp | Issued document and release event | End of this initial-issue cycle |
| Handoff and correction evidence | Drawing, quote, revision and decision references | Which missing input or rework caused waiting? |
| Stage owner and waiting reason | Owner response tied to the source event | Who can change the next repeated bottleneck? |
| Later amendments | Separate approved change-order history | Preserve rework without adding it to the initial clock |
For this simplified audit, three stages are sequential: received to complete, complete to final approval, and approval to PO release. If quotes and approvals run in parallel, map their actual intervals separately and retain the end-to-end clock. Do not add overlapping stage durations as if they happened one after another.
Reconstruct the ten fictional timestamp chains
| Order | Request received | Request complete | Final approval | PO released |
|---|---|---|---|---|
| A01 | Nov 02 09:00 | Nov 02 13:00 | Nov 03 13:00 | Nov 03 21:00 |
| A02 | Nov 03 09:00 | Nov 03 17:00 | Nov 05 05:00 | Nov 05 17:00 |
| A03 | Nov 04 09:00 | Nov 04 13:00 | Nov 06 13:00 | Nov 06 21:00 |
| A04 | Nov 05 09:00 | Nov 05 21:00 | Nov 06 21:00 | Nov 07 09:00 |
| A05 | Nov 06 09:00 | Nov 06 17:00 | Nov 09 05:00 | Nov 09 13:00 |
| A06 | Nov 07 09:00 | Nov 07 13:00 | Nov 09 01:00 | Nov 09 13:00 |
| A07 | Nov 08 09:00 | Nov 08 21:00 | Nov 10 21:00 | Nov 11 13:00 |
| A08 | Nov 09 09:00 | Nov 09 17:00 | Nov 12 17:00 | Nov 13 01:00 |
| A09 | Nov 10 09:00 | Nov 10 13:00 | Nov 12 01:00 | Nov 12 13:00 |
| A10 | Nov 11 09:00 | Nov 11 17:00 | Nov 13 17:00 | Nov 14 05:00 |
Each event has a synthetic source reference using its order prefix, such as A03-REQ, A03-COMPLETE, A03-APPROVAL and A03-ISSUE. In an actual audit, retain the retrievable record and version behind the timestamp. A row copied from an export without its date meaning is not sufficient evidence.
| Order | Completeness | Approval | Release | Total |
|---|---|---|---|---|
| A01 | 4 | 24 | 8 | 36 |
| A02 | 8 | 36 | 12 | 56 |
| A03 | 4 | 48 | 8 | 60 |
| A04 | 12 | 24 | 12 | 48 |
| A05 | 8 | 60 | 8 | 76 |
| A06 | 4 | 36 | 12 | 52 |
| A07 | 12 | 48 | 16 | 76 |
| A08 | 8 | 72 | 8 | 88 |
| A09 | 4 | 36 | 12 | 52 |
| A10 | 8 | 48 | 12 | 68 |
| Median, n = 10 | 8 | 42 | 12 | 58 |
A03 illustrates the arithmetic: November 4 at 09:00 to November 4 at 13:00 is four hours, then 48 hours to approval and eight to release. Its total is 4 + 48 + 8 = 60 hours. For the ten total durations, the sorted middle pair is 56 and 60, so the median is (56 + 60) ÷ 2 = 58 hours, about 2.42 calendar days.
The total elapsed time is 612 hours across ten orders, so the mean is 612 ÷ 10 = 61.2 hours, or 2.55 calendar days. The independently calculated stage medians are eight, 42 and twelve hours. Their sum is 62, not 58. This is expected: adding medians does not reconstruct the median order.
Use the source events to choose the first fix
The approval stage has the largest median in this sample. Inspect the long cases before declaring that approvals should be removed. In the teaching record, A08 waited 72 hours because the required approver was unavailable and no delegate was assigned. A05 waited 60 hours for a missing cost-code decision. Those causes require different changes.
| Finding | Evidence and consequence | Owner and test |
|---|---|---|
| No approval delegate on A08 | 72-hour approval interval, availability note A08-WAIT | Spending owner defines permitted coverage and tests it on the next comparable request |
| Cost code unresolved on A05 | 60-hour approval interval, A05-CODE question | Requester and finance add the needed code or an explicit resolution owner before approval |
| Two later corrections | A04 had wrong ship-to data, A08 had a quote-version correction | Preserve separate 12-hour and 24-hour amendment paths, improve pre-issue readback |
Two of the ten orders later needed those initial-data corrections: 2 ÷ 10 = 20% of this defined sample. Their 12-hour and 24-hour change-order durations are separate from the initial 612 hours. They establish no stable long-run error rate. Keep the initiating reason and approval history so design-driven changes are not mislabeled as buyer mistakes.
Elapsed time includes working and waiting. It is not 42 hours of active approver effort. If effort matters, collect touches and work minutes separately. The first test here is approved delegation plus complete cost-code routing, not faster approval by bypassing technical or spending authority.
po_id,initial_version,requisition_refs,request_received_at,request_complete_at,final_approved_at,po_released_at,time_zone,calendar_basis,completeness_hours,approval_hours,release_hours,total_hours,source_refs,waiting_reason,stage_owner,later_amendment_ref
completeness_hours = request_complete_at - request_received_at
approval_hours = final_approved_at - request_complete_at
release_hours = po_released_at - final_approved_at
total_hours = po_released_at - request_received_at
Repeat the same measurement after the change
Assign a date and owner to the improvement, then repeat the audit with the next ten comparable orders using the same endpoints and scope. Retain incomplete chains as gaps, compare the median, mean and range, and inspect whether work moved into another stage or generated more rework. A faster total is useful only if the release still carries the correct part, quantity, terms and approvals.
Oracle’s requisition overview describes the internal request and buyer-order handoff. The robotics requisition template helps make that request complete. The field-ownership guide helps locate the authoritative sources. If you later compare operating tools, use those measured needs in the same-order procurement comparison rather than turning this audit into a vendor ranking.
Frequently asked questions
Does requisition-to-PO cycle time include weekends?
This audit uses elapsed timestamp hours, including nights, weekends and closures. It starts when the request reaches purchasing and ends when the initial approved PO is released to the supplier. You can also report working time under a stated calendar, but keep it separate and never mix the two conventions in one summary.
Can I add the median times for each stage to get the total median?
No. Medians are calculated independently and need not come from the same order. Here the stage medians are 8, 42 and 12 hours, totaling 62, while the median of the ten end-to-end durations is 58 hours. Calculate each order’s total from its own timestamps first.
What should I do when one order has no approval timestamp?
Keep that order in the selected sample and mark the stage unresolved. Recover the source if possible, then state the number of complete observations behind each summary. Do not enter zero, infer approval from the PO date or silently discard the incomplete order to improve the result.