Compare supplier quotes for robotics parts against the same released drawing, delivered scope and usable receipt date. Calculate the quantity you must buy, the cash due at each payment milestone and the cost per accepted unit. Then check how many compatible parts could be ready for assembly by the date you need them.

Give every offer the same technical scope

The illustrative civilian R-PILOT sourcing example needs five BRK-101 Rev C brackets, one per robot, with no accepted stock or spare allowance. BRK-101 is a 6061-T6 aluminium sensor-support bracket. The buyer supplies matching STEP and dimensioned PDF references, the selected finish, fit-critical characteristics and the required inspection records. All prices, suppliers and commitments below are invented teaching inputs.

Use the robotics BOM RFQ template to preserve the requested scope beside each reply. Record exceptions before calculating a ranking. A supplier offering another drawing revision, omitting finishing or leaving the inspection scope unanswered needs a decision from the relevant owner.

Specify whether inspection occurs after the required finish and whether the quoted price includes the report. Xometry distinguishes standard inspection from options that include a dimensional report. Its published standard inspection description says documentation is not shipped with the parts. Check the selected service in the actual quote. Xometry inspection options.

Copy a quote comparison record

Copy this blank table into a spreadsheet or purchasing record. Use one supplier column per offer and keep a link to the exact quote version. Leave unanswered fields visibly unresolved.

Blank supplier quote comparison
FieldSupplier ASupplier B
Quote reference, date, currency and expiry
Part, drawing revision and supplied files
Material, finish and inspection scope
Required quantity, MOQ and order multiple
Purchase quantity and unit price
Setup, tooling charge and tooling ownership
Separate finishing and inspection charges
Freight, tax, duty and other charges
Known total and unresolved costs
Payment milestones and cash due now
Dispatch date, arrival date and receiving allowance
Quantity projected usable by the issue date
Approval owner, decision and remaining conditions

Purchase quantity is the smallest permitted order that covers demand after accepted stock and valid allocations. Apply the supplier’s MOQ and order multiple together. Confirm how the multiple works when an offer states, for example, a minimum of seven with packs of five.

Work through two five-robot offers

Both teaching offers cover BRK-101 Rev C, the same material, finish and post-finish dimensional checks. The example uses USD and domestic freight. Sales tax is excluded by an explicit teaching assumption. Both offers require the known total on award, and neither includes an expedite service. A real comparison needs confirmed tax, duty and expedite treatment.

Illustrative five-robot bracket quote costs
Cost inputSupplier ASupplier B
MOQ and order multiple1 and 110 and 5
Purchase quantity5 brackets10 brackets
Unit price and extended part price$80 × 5 = $400$45 × 10 = $450
Setup$100$100
Finishing$25$50
Inspection report$50$50
Freight$25$30
Known total and cash due on award$600$680
Expected cost per accepted unit if the whole lot passes$600 ÷ 5 = $120$680 ÷ 10 = $68

The setup charge pays for preparation in this exercise. It creates no customer-owned reusable tooling asset. An actual tooling offer should name the owner, storage location, maintenance responsibility and release or transfer terms.

Illustrative usable delivery and demand coverage
Delivery inputSupplier ASupplier B
Finished parts at the receiving site5 by Wednesday 2 December 20265 by Wednesday 2 December and 5 by Friday 4 December
Material issueThursday 3 December 2026Thursday 3 December 2026
Projected usable quantity by issue5, if receiving checks pass5, if receiving checks pass
Demand covered and surplus purchased5 covered and 0 surplus5 covered and 5 surplus

Supplier A requires $80 less cash for this five-unit demand. Supplier B has a lower expected cost per accepted unit across its ten-unit lot. The buyer must decide whether the five extra Rev C brackets have an approved future use and whether their storage and revision risk justify the additional purchase.

Use actual accepted quantities when receipts are known. A projected cost per accepted unit assumes the chosen parts pass. It cannot establish supplier yield. For comparison, retain the quoted total, the quantity basis and the later receiving result.

Check a separate 20-robot lot by date

A separate scaled exercise needs two BRK-101 Rev C brackets per robot, so 20 robots require 40 brackets. This changes the demand from the five-robot pilot above. There is no accepted stock. Here finishing and the agreed inspection report are included in the unit price, and the setup and freight charges are the only additional known costs.

Illustrative quotes for 40 required brackets
ComparisonSupplier ASupplier B
Permitted order44 at $24 each50 at $19 each
Setup and freight$250 and $45$400 and $70
Known total, fully prepaid44 × $24 + $250 + $45 = $1,35150 × $19 + $400 + $70 = $1,420
Expected whole-lot cost per accepted bracket$1,351 ÷ 44 = $30.70 rounded$1,420 ÷ 50 = $28.40
Projected usable brackets by issue4420, with the remaining 30 later
Robots covered by this bracket line20, with 4 brackets left10, with 20 brackets short

These projected usable counts assume the specified receipt checks pass. Supplier B’s whole-lot unit cost leaves half the robot demand uncovered at issue. Any proposed expedite, duty or additional shipment charge remains an unresolved cost until confirmed. Keep the late 30 units visible in the time-phased record.

Record the award and its conditions

Save the chosen offer version, approved scope, purchase quantity, price breakdown and receipt commitments. Name the buyer, technical reviewer and any quality conditions. ASQ includes delivery reliability, incoming verification and total supplier cost in its supplier-quality guidance. ASQ supplier quality.

After award, use the supplier PO acknowledgement record to reconcile the supplier’s actual reply with the issued order. A changed delivery proposal needs its own buyer decision and coverage calculation.

Arc’s published sourcing workflow links selected parts, drawing references and available quotes for engineering review. In a demo, inspect whether those references make each unresolved quote condition easy for your team to review.

Questions about robotics quote comparison

How should I compare quotes with different minimum order quantities?

Calculate each permitted purchase quantity from the same net demand, then apply its unit price and all known lot charges. Show surplus, cash timing and projected usable quantity by the required date. Keep the accepted-unit cost calculation tied to the quantity that actually passes receipt checks.

What if a quote excludes the dimensional report we need?

Ask the supplier to price and confirm the required report against the specified drawing revision and inspection scope. Keep that offer unresolved until the relevant quality owner accepts the scope and the buyer has the complete price.

Can the lowest cost per accepted unit still leave the build short?

Yes. In the scaled example, Supplier B costs $28.40 per bracket if all 50 pass, but only 20 are projected usable at issue. The 40-bracket demand is therefore 20 short. Calculate delivery coverage separately from whole-lot cost.

Move faster without compromising engineering rigour.

Bring two bracket quotes and their drawing references to an Arc demo. Review the quantity, revision and unanswered delivery questions beside the selected BOM line.