Reconcile consigned components for PCB assembly by matching customer-supplied receipts to fitted parts, approved scrap, confirmed returns and the closing stock held by the assembler. Keep the component identity, stock lot, owner and location visible. A balanced ledger explains where the parts went and which quantity is available for the next build.
Agree the free-issued material boundary
For each BOM line, state whether the customer supplies the component or the assembler purchases it. Agree delivery packaging, receipt counting, storage, handling, permitted process losses and the return or retention of surplus. Record how shortages and disputed scrap are escalated and who pays for replacements under the actual contract.
MacroFab describes customer-furnished materials drawn from existing customer inventory or shipped to it as consigned parts. That first-party example establishes the distinction between inventory allocation and a new consignment. The reconciliation and approval record below is a proposed working method for your own assembly agreement. MacroFab customer-furnished material guidance.
When comparing assemblers, confirm their actual receipt, lot control and surplus-return arrangements. The Bay Area PCB fabrication and assembly directory provides candidate sources and the questions to resolve for a small job.
Copy a component and balance record
Use one ledger per component identity and stock lot at each contractor site. Keep receipts, transfers and returns as separate events. Copy these blank tables into the job record.
| Field | Value or evidence reference |
|---|---|
| Assembly job, board part and selected revision | |
| Component MPN, BOM reference designators and quantity per board | |
| Customer owner, contractor site and stock lot | |
| Consignment packing list and contractor receipt count | |
| Allowed process overage and scrap approval rule | |
| Storage location and usable, reserved or held status | |
| Surplus return or retention decision | |
| Ledger owner, reconciliation date and sign-off |
| Balance category | Quantity | Evidence and owner |
|---|---|---|
| Opening stock at contractor | ||
| Receipts counted during the period | ||
| Fitted to identified assemblies | ||
| Approved process scrap | ||
| Confirmed surplus returns | ||
| Return-in-transit quantity at the cut-off | ||
| Closing stock physically held at contractor | ||
| Unresolved variance |
For a single-site lot, variance equals opening stock + counted receipts − fitted quantity − approved scrap − confirmed returns − return-in-transit quantity − closing stock. Give each component one category at the cut-off. Record disputed or missing quantities in the variance and assign an investigation owner.
Reconcile seven connectors for five boards
The illustrative civilian R-PILOT build needs five PCB-301 Rev C assemblies. Each board uses one customer-supplied CON-301 connector at J1. The customer free-issues seven connectors from stock lot CON-L01 to assembly job ASM-301. The board, connector identity, lot, agreement and events are fictional.
The teaching agreement reserves five connectors for the five boards and allows two extra pieces to be sent. It requires customer approval of recorded process scrap. Extra material sent and material actually scrapped have distinct ledger entries.
| Category | Quantity | Location or evidence | Responsible owner |
|---|---|---|---|
| Opening contractor stock | 0 | No previous CON-L01 balance | Contractor materials owner |
| Counted consignment receipt | 7 | Receipt CFM-301 and customer packing list | Contractor receiving owner |
| Fitted to PCB-301 Rev C | 5 | J1 on board identities P301-01 through P301-05 | Contractor assembly owner |
| Approved process scrap | 1 | Scrap record SCR-301 identifies the damaged component and customer approval | Customer materials owner |
| Confirmed surplus returns | 0 | Return has not occurred at this cut-off | Customer receiving owner |
| Closing contractor-held stock | 1 | Customer-owned CON-L01 in shelf CFM-A2, reserved and held pending return instruction | Contractor materials owner |
The checked balance is 0 + 7 − 5 − 1 − 0 − 1 = 0 unresolved variance. Five connectors are fitted, one has approved scrap evidence and one remains customer-owned at the contractor. The retained connector is excluded from available stock for another job until its status and allocation are approved.
If the assembler reports two scrapped connectors while holding none, the same arithmetic may balance. The customer still needs the second scrap occurrence and approval evidence. A quantity balance cannot establish that an unapproved loss is acceptable.
Close the surplus return with physical readback
The customer instructs the assembler to return the held connector under RET-301. Record dispatch, tracking and customer receipt as separate events. At this example’s reconciliation cut-off, a confirmed return requires the customer’s count and lot readback. Until that evidence exists, record the dispatched item in the return-in-transit category with its tracking reference and owner.
| Category | Quantity | Readback |
|---|---|---|
| Original receipt | 7 | CFM-301 unchanged |
| Fitted and approved scrap | 5 fitted and 1 scrap | Assembly and SCR-301 evidence unchanged |
| Confirmed return | 1 | Customer receives CON-L01 against RET-301 |
| Closing contractor stock | 0 | Contractor confirms shelf balance zero |
| Variance | 0 | 7 − 5 − 1 − 1 − 0 = 0 |
At the customer site, count the returned connector into the correct lot and inspect its condition before changing it to usable stock. Keep its ownership and reservation clear. The contractor’s zero closing balance and the customer’s receipt should describe the same physical transfer.
Keep material balance and board acceptance connected
Five fitted connectors establish consumption for five board identities. PCB acceptance still requires the agreed assembly and test results against PCB-301 Rev C. Link the component lot and reconciliation to the robot build record, with the board receiving decision and any hold visible.
Before a repeat job, confirm retained stock, condition, allocations, changed component identities and the assembler’s current requirement for overage. Arc’s published BOM and sourcing workflow brings selected board revisions and supporting supplier documents into human review. Use a demo to inspect those references alongside the consignment questions.
Questions about consigned component reconciliation
Does a zero component variance mean the PCB assemblies are accepted?
A zero variance accounts for the component quantities at the ledger cut-off. Board acceptance requires the assembly and test evidence agreed for the selected revision. Record the PCB receiving disposition separately from the component balance.
Can the assembler count an unused connector as scrap?
Use the agreed scrap definition and approval rule. The example’s unused connector remains customer-owned stock pending return instruction. Scrap needs an identified occurrence and the required customer approval before entering the approved-scrap balance.
When should a returned component leave the contractor-held balance?
Use a defined transfer policy and record dispatch, transit and customer receipt. This example moves the unit into confirmed returns after customer receipt readback. Count it in one closing category at each cut-off and preserve the lot identity through the transfer.