On this page

Costed robotics BOM example, calculating one, ten and one hundred finished units

Calculate consumed material BOM costs by multiplying each quantity per robot by its price in the matching unit, then summing the lines. Add the material spend allowance, assembly labour and allocated lot fixtures separately. Check pack sizes and minimum orders in a separate cash-outlay calculation before purchasing.

This worked model uses R-01, a fictional indoor inspection robot, at design B. It compares three independent lots of 1, 10 and 100 finished robots. Every robot uses HR-300 B. These scenarios are separate from the mixed five-unit pilot with two A harnesses and three B harnesses.

All prices are illustrative GBP estimates prepared for this example on 19 November 2026. They are not supplier quotes or evidence of market prices, negotiated discounts or achieved assembly times.

Calculate material cost from purchased leaves and consumables

Each robot contains two in-house DM-100 A drive modules. Cost the motors, brackets and screws used to build them. Adding a purchased price for DM-100 as well would count the same material twice.

CB-200 A is purchased as a complete PCBA, so include its assembly price and omit separate electronic children. The sensor hardware kit is a virtual grouping of two screws already included in the ten-per-robot total. It adds no purchase cost. AD-900 is consumed during manufacture at 2 mL per robot.

Item and revision Quantity per robot Price unit Unit price at lot 1 Unit price at lot 10 Unit price at lot 100
MT-110 A motor 2 ea £45.00 £41.00 £35.00
BR-120 A bracket 2 ea £18.00 £15.00 £10.00
SC-130 A screw 10 ea £0.20 £0.15 £0.08
CB-200 A complete PCBA 1 ea £72.00 £60.00 £48.00
HR-300 B harness 1 ea £18.00 £15.00 £11.00
SN-400 A sensor 1 ea £35.00 £33.00 £28.00
CH-500 A chassis plate 1 ea £42.00 £35.00 £25.00
AD-900 consumable 2 mL £0.12 £0.10 £0.08

Multiply quantity per robot by the price in the matching unit. The BOM template explains the ten-screw quantity. The manufacturing mapping explains the process material and complete-PCBA boundary.

Material cost per robot Lot 1 Lot 10 Lot 100
Two motors £90.00 £82.00 £70.00
Two brackets £36.00 £30.00 £20.00
Ten screws £2.00 £1.50 £0.80
Complete PCBA £72.00 £60.00 £48.00
B harness £18.00 £15.00 £11.00
Sensor £35.00 £33.00 £28.00
Chassis plate £42.00 £35.00 £25.00
Two mL consumable £0.24 £0.20 £0.16
Material total per robot £295.24 £256.70 £202.96

Add the spend allowance, labour and fixtures

The model adds a 2% spend allowance on material cost. It is a budget allowance, with no claim about yield, scrap rate or the number of parts to order. If the real process needs spare harnesses or extra screws, model those quantities explicitly.

Labour is £40 per hour. Assembly takes an assumed 2 hours per robot in the one-unit lot, 1.5 hours in the ten-unit lot and 1 hour in the hundred-unit lot. Lot fixtures cost £0, £120 and £500 respectively. Allocate each fixture cost across the corresponding finished quantity.

Use these equations in Excel, Google Sheets or another calculation tool. N is the finished lot quantity, M the material cost per robot, H the labour hours per robot and F the fixture cost for the lot.

M = SUM(quantity_per_robot * price_per_matching_unit)
Unrounded cost per robot = M * 1.02 + H * 40 + F / N
Unrounded lot cost = N * (M * 1.02 + H * 40) + F
Reported outputs = ROUND(unrounded output, 2)
Roll-up assumption or output Lot 1 Lot 10 Lot 100
Material per robot £295.24 £256.70 £202.96
Material spend allowance 2% 2% 2%
Labour hours per robot 2 1.5 1
Labour cost per robot £80.00 £60.00 £40.00
Fixture cost per lot £0.00 £120.00 £500.00
Fixture allocation per robot £0.00 £12.00 £5.00
Reported cost per robot £381.14 £333.83 £252.02
Reported lot cost £381.14 £3,338.34 £25,201.92

Keep full precision through the calculations and round only the reported outputs. For ten units, the unrounded unit cost is £333.834. Multiplying the displayed £333.83 by ten would lose four pence. At one hundred units the unrounded unit cost is £252.0192, so multiplying the displayed unit figure would add eight pence.

Check cash outlay separately from consumed cost

For an actual purchase, record supplier quote date, quantity break, currency, pack size, minimum order quantity and revision. A pack price must be converted to a per-piece basis before using this table. The order still needs whole packs and may leave unused stock.

AD-900's per-mL cost is consumed cost. A real container's purchase price, usable shelf life and residual stock affect cash and waste separately. The sensor's internal ID SN-400, synthetic MPN SEN-X12 and distributor SKU DIST-1204 should stay distinct when matching a quote.

This model excludes freight, tax, overhead, testing, rework, warranty, financing and other costs that a real budget may require. Fixture reuse across later lots is also a separate decision. The lower estimates at larger lots come from the stated inputs, rather than a measured production result.

Before using a costed BOM for approval, reproduce one line and the complete lot equation independently. Then replace estimates with dated quotes and an agreed labour basis. Preserve the selected product configuration beside the cost model so a price comparison cannot silently switch the design.

Move faster without compromising engineering rigour.

Review one product release, its change decisions and supporting evidence with Arc.