Generate a purchase-order draft from a released BOM by calculating demand, netting usable stock and timely confirmed supply, then reconciling every existing order before selecting a supplier. The draft should identify the approved part, revision, quantity, price and delivery terms. A buyer approves the final version before Arc records it in the configured ERP and sends it to the supplier.
WR-12 is a fictional 12-robot build. It requires 24 BRK-140 Rev D brackets. Its sourcing and PO snapshots below have different dates: do not turn the same eight-piece gap into two purchases.
Compare the pre-order and post-order snapshots
| Snapshot | Compatible supply and demand | Buyer action |
|---|---|---|
| December 2, before B’s order | 24 gross − 4 usable − 12 correctly scoped A on order = 8 to source | Seek and compare offers for eight; the 12 ordered are not stock |
| Quote review | B: 8 × USD 72 + USD 40 tooling + USD 24 freight = USD 640 before tax; MOQ 8 | Check Rev D, lot, validity, taxes and delivery; C’s comparable offer totals USD 680 |
| December 7, after B’s PO | 10 D accepted, six A still open and eight B ordered; B is undated | Do not create another eight-piece PO; resolve timing and retain both existing balances |
| Friday issue | 10 accepted + six A forecast usable = 16 of 24; eight short | Ask whether B can advance or agree a reconciled recovery |
| Later forecast | B’s accepted Friday dock forecasts Monday usable under the one-business-day rule | Keep forecast conditional on QA/put-away and NPI decision |
At the earlier quote stage, B’s and C’s offers were valid through December 4. A new award review on December 7 requires renewed validity. An already approved B PO remains its own historical record; a later expiry does not erase the order. B’s MOQ is eight, so the eight-piece reviewed quantity satisfies it. For a larger MOQ or purchase multiple, show the rounded quantity, excess and demand permission before approval.
Review the draft, then check the readback
| Field | Evidence to match | Hold if missing |
|---|---|---|
| Part and release | BRK-140 Rev D, DW-BRK-140-D-R1, unit ea and the selected BOM line | Released scope, destination or revision differs |
| Supplier and terms | Approved supplier, current quote version, price, currency, tooling, freight, tax and validity | Offer expired, wrong revision or an incomplete commercial basis |
| Quantity and dates | Net demand, MOQ/multiple, need-by, agreed dock and schedule identities | Existing PO or receipt is counted twice, or a date is merely proposed |
| Authority | Buyer approval of final PO and engineering approval of substitution | A changed draft has not returned for approval |
| After approval | Configured ERP PO/version and supplier message readback | The recorded quantity, supplier, revision or terms differ from the approved draft |
Arc can draft POs for the shortfall using released BOM, inventory and open-order records. The buyer chooses the supplier and approves the final purchase. An agent can then record it in the configured ERP and send the approved version; an edited version returns for approval. Engineering decides whether a substitute meets the specification. A receiving team owns actual acceptance and stock release.
Use the BOM buying-list guide to check gross demand and the open-PO tracker to follow the approved order. This example does not create a real PO or demonstrate a specific ERP connector.
Frequently asked questions
Is the BOM quantity the purchase quantity?
The BOM gives gross build demand. Deduct eligible unreserved stock and compatible confirmed supply by the required date, then reconcile existing orders and purchase constraints before approving a PO.
Should I issue a second PO for a late existing order?
Not automatically. Keep the late order visible and decide whether to advance, amend or cancel it. Any bridge purchase must account for the retained commitment and the buyer’s agreed disposition.
What happens after the buyer approves a draft PO?
In the configured workflow, Arc records the approved PO in the ERP and sends it to the supplier. Check the ERP readback and outgoing version. A later edit returns for approval before it takes effect.