Material requirements planning (MRP) software should tell a robotics manufacturer which approved parts are needed, in what quantity and by which date. In this illustrative twenty-robot batch, the team is short of four controllers and five replacement actuators on 14 December. Existing later orders cover the controller quantity and three actuators. The decision is whether to secure earlier delivery or split the build, and when to order two additional actuators.
Choose an MRP system by reproducing that dated calculation with your own bill of materials, stock reservations and supplier orders. A well-maintained sheet can still do it for a small plan. Dedicated software becomes useful when several batches, subassemblies or receipt changes make the reconciliation difficult to maintain.
What does material requirements planning calculate?
MRP converts a production requirement into component quantities, subtracts eligible supply and works backwards through lead times. Its inputs include the build schedule, bill of materials (BOM), on-hand balances and scheduled receipts. Its outputs are proposed purchase, production or rescheduling actions. Oracle MRP overview · SAP MRP explanation
The useful result is a dated plan. A component arriving after material issue cannot cover that issue, even when an aggregate stock forecast is positive. Keep the physical count, usable quantity, due receipts and proposed orders separately visible.
Material availability also needs a separate capacity check. People, workstations, tooling, inspection and assembly time determine when the robot can be completed. Oracle's overview explicitly distinguishes its material plan from capacity verification. A materials calculation should not become a shipment promise.
Start with the accepted robot configuration
WP-200 is a fictional warehouse picking robot with two orderable items. WP-200-J uses a jaw gripper. WP-200-V uses a vacuum gripper. Each robot needs one CH-110 A chassis and one CTL-310 B controller bought complete.
REL-WP-01 was approved on 30 October 2026. Five jaw robots, WP-001–WP-005, were built on 6 November using BOM-JAW A and CFG-JAW A. Their GR-J210 A grippers contain ACT-410 A actuators and ENC-510 A encoders, with FW-310 1.4.0 installed on the controller. VAC A was qualified in that original release.
Actuator availability prompts engineering change order ECO-027, approved on 18 November. REL-WP-02 is issued on 19 November for batch B-2412, with the following selections. All parts, dates and planning results are teaching inputs.
| Planned robot | Quantity and serials | Selected gripper structure | Firmware on CTL-310 B |
|---|---|---|---|
| WP-200-J, BOM-JAW B / CFG-JAW B | 12, WP-006–WP-017 | One GR-J210 B, containing one ACT-420 A and one ENC-520 A | FW-310 1.5.0 |
| WP-200-V, BOM-VAC A / CFG-VAC A | 8, WP-018–WP-025 | One GR-V220 A, containing one PMP-430 A pump. No jaw encoder | FW-310 1.4.0 |
DW-GR-J210 B and fictional verification reference TV-027 support the exact new jaw combination. Earlier serials retain their A drawing and as-built release, with no retrofit. Eight usable ACT-410 A actuators remain for that legacy design. They contribute zero supply to the JAW B plan.
Approve the engineering-to-manufacturing BOM mapping before planning purchases. Mark grippers as made assemblies and controllers as bought-complete inputs. Firmware is a controlled installation requirement, with no purchased-stock demand. Keep REL-WP-02 on the planning records so a buyer can trace the selected item revisions. The BOM build-package guide covers that mapping, and the PLM guide covers the change approval and build applicability. Product lifecycle management (PLM) supplies the accepted engineering context.
Calculate gross demand and usable supply
The planning snapshot is 20 November 2026. All twenty robots require material issue on 14 December. There are no prebuilt grippers. Other approved physical inputs, including twelve ENC-520 A encoders, twenty chassis and eight pumps, are assumed sufficient.
The fixture uses unit purchase multiples, zero safety stock and no extra time for inspection, staging or gripper operations. Lead times are elapsed calendar days from order confirmation to usable receipt in the build warehouse. Real plans should include those omitted times and any supplier pack constraints.
The common controller requirement is 12 × 1 + 8 × 1 = 20. The jaw actuator requirement is 12 robots × 1 gripper × 1 actuator = 12. Gripper manufacture generates those child requirements once.
Table 1 separates physical stock from the quantity the batch may use.
| Item revision | Gross requirement | Physical stock | Unavailable to B-2412 | Usable stock | Standard lead time |
|---|---|---|---|---|---|
| CTL-310 B | 20 | 12 | 2 reserved to another job | 10 | 14 calendar days |
| ACT-420 A | 12 | 4 | 1 quarantined | 3 | 28 calendar days |
An item counts as usable only if the selected revision is accepted, it is in the chosen supply scope, and it is free for this batch. Count the unrelated controller reservation once. Keep quarantined stock visible while excluding it from available supply.
Which receipts arrive before material issue?
Table 2 gives the four existing purchase-order receipts. A purchase order (PO) records ordered supply. A planned or quoted date still needs confirmation and later receipt acceptance.
| Item revision | Open quantity | Usable receipt date in the fixture | Counts for 14 December issue? |
|---|---|---|---|
| CTL-310 B | 6 | 8 December | Yes |
| CTL-310 B | 5 | 17 December | No |
| ACT-420 A | 4 | 9 December | Yes |
| ACT-420 A | 3 | 18 December | No |
For this single dated demand, calculate net gap = max(0, gross requirement − usable stock − eligible receipts). For several dates, carry the remaining balance forward and consume each receipt only once.
| Item revision | Calculation for 14 December | Covered quantity | Net gap |
|---|---|---|---|
| CTL-310 B | 20 − (12 − 2) − 6 |
16 | 4 |
| ACT-420 A | 12 − (4 − 1) − 4 |
7 | 5 |
This is why the later orders must remain in the forward plan. After all existing receipts, controllers total 10 + 6 + 5 = 21, leaving one beyond this batch. Replacement actuators total 3 + 4 + 3 = 10, leaving a genuine quantity gap of two. The issue-date shortage and the eventual additional purchase quantity lead to different actions.
What should the buyer purchase or reschedule?
Work backwards from usable receipt on 14 December. At the standard lead time, a controller order can be confirmed by 14 December − 14 days = 30 November. An actuator order would need confirmation by 14 December − 28 days = 16 November. That actuator date has already passed at the 20 November snapshot.
A new standard actuator order confirmed on 20 November arrives on 18 December in this fixture. It cannot solve a 14 December issue gap without a confirmed faster delivery arrangement.
Table 3 is an action ledger for the original plan. Every action remains a proposal until the responsible planner and buyer accept it.
| Planning problem | Concrete action to assess | Evidence before changing the build plan |
|---|---|---|
| Four controllers missing at issue | Request four of the five due on 17 December to arrive earlier. A bridge purchase is another option if reconciled with that existing order | Accepted quantity/date, warehouse receipt readiness and disposition of any overlapping later supply |
| Five actuators missing at issue | Seek confirmed faster supply, split the jaw build or combine both actions | Approved ACT-420 A identity, firm delivery dates and retained ENC-520/FW compatibility |
| Two actuators still missing after all existing orders | Order two additional ACT-420 A, subject to supplier confirmation and the chosen split plan | Genuine remaining demand, lead time, existing PO references and required receiving checks |
| Build completion after material arrival | Check gripper operations, assembly and acceptance capacity separately | A feasible workstation/personnel plan and revised completion dates |
If the planner prioritises all eight VAC robots on 14 December, they consume eight of the sixteen covered controllers. Eight controllers remain, but only seven JAW B actuator inputs are available. The material-complete allocation is therefore eight VAC plus seven JAW, or fifteen kits.
The remaining five jaw robots can receive five controllers on 17 December. Three actuators already due on 18 December plus two additional actuators ordered at the standard lead time on 20 November can cover their actuator requirement on 18 December, if the dates are promised and receipts accepted. Actual assembly completion depends on capacity. This split does not authorise fitting legacy actuators to JAW B.
When is a planning sheet sufficient?
A sheet can serve a small team when an owner maintains the accepted BOM, dated demand, stock status, reservations and every open receipt. Keep a saved planning snapshot, protect formula cells and require review of purchase and rescheduling actions. Another person should be able to reproduce the four-controller and five-actuator gaps from the inputs.
It becomes harder to maintain when several builds compete for the same controller, subassembly stock changes, or supplier dates move frequently. Evaluate software when those changes cause recurring missed demand, double allocation or duplicate purchase proposals. Increasing the number of products does not remove the need for accurate source data.
Which workflow should MRP software support?
Select the smallest operating model that meets the team's repeated planning job. The options below are qualitative workflow choices, with no vendor ranking.
| Team situation | Workflow worth evaluating | Acceptance condition |
|---|---|---|
| One stable low-volume batch and a reliable owner | Controlled sheet connected to current stock and receipt records | Reproduce each dated gap and maintain the action ledger |
| Several batches and made subassemblies share parts | Manufacturing MRP with inventory and purchasing | Allocate shared supply once and retain each batch's need date |
| Manufacturing must share finance, sales and warehouse records | An enterprise resource planning (ERP) system with the relevant manufacturing modules | Planning, stock and purchasing reconcile under the selected modules and permissions |
| Source rights and self-hosting are buying requirements | An open-source manufacturing evaluation | Verify licences, operational ownership and the exact dated report/order workflow |
The Odoo Community and ERPNext comparison examines the last option using this same plan and one delayed receipt. The engineering-to-manufacturing BOM guide helps define the accepted input before choosing any of these workflows.
Use the twenty-robot plan as the software checklist
This guide is for robotics founders, manufacturing engineers and operations leads moving from prototypes into low-volume production. Its method compares observable planning workflows against one fictional batch. Oracle's historical MRP overview and SAP's category explanation were inspected on 20 November 2026 for the planning principles. They establish conceptual scope and do not form a current product shortlist.
The existing buyer-guide methodology provides a reference for evidence and unknowns. Here the criteria are qualitative, with no numerical scores or aerospace weights. Arc is a software vendor and has a commercial interest in software evaluations. No live MRP instance, comparative benchmark or customer result was tested.
| Buyer check | Evidence to request from the intended edition and setup |
|---|---|
| Multi-level make/buy | Twelve jaw grippers create demand for twelve actuators. The controller appears as one purchased assembly per robot |
| Approved configuration | BOM-JAW B and BOM-VAC A remain selected, with exact item revisions and REL-WP-02 traceability |
| Reservations and holds | Physical 12/4 becomes usable 10/3. The unrelated reservation and quarantine are explainable |
| Dated shortage | Later receipts stay visible and the 14 December gap remains four controllers and five actuators |
| Supplier and order action | Lead time produces the latest standard order dates. An earlier existing receipt can be distinguished from genuine additional purchase quantity |
| Shared subassemblies and locations | Chosen stock, work-in-progress and supplier-held or consigned quantities have clear ownership and availability rules |
| Contract manufacturing | Supplied material, bought assemblies and contractor receipts are counted once, with accepted source/release references |
| Export and repeatability | Another planner can reproduce demand, usable supply, eligible receipts and approved actions from a dated export |
Record the actual software version, modules, warehouse scope, permissions and settings beside the observed outputs. If an automatic proposal differs from the fixture, inspect horizons, safety stock, lot sizes, reservations and due dates before accepting it. An unexplained difference remains unresolved.