Track a custom-part PO through agreed production milestones tied to the order line, released drawing and required evidence. Keep planned completion beside supplier-reported completion. Use the remaining work and agreed ship date to decide whether to follow up, recover production time or request a revised commitment.
Start after the supplier commitment has been reconciled. This guide owns the interval between that acknowledgement and shipment: material and fixture readiness, first-off sample, finishing, inspection and dispatch. A milestone can be a working agreement without becoming a payment or acceptance event. Define its meaning with the supplier.
Make each milestone an evidence request
| Milestone and PO line | Planned completion | Actual or proposed completion | Evidence required | Owner and next decision |
|---|---|---|---|---|
| Material or bought-in input ready | Traceable available input for the ordered scope | |||
| Fixture and program ready | Approved setup or readiness record | |||
| First-off sample reviewed | Selected characteristics, methods and reviewer | |||
| Required finish complete | Lot identity and processor evidence if required | |||
| Final inspection and document package complete | Agreed report and part/lot coverage | |||
| Dispatched | Carrier reference, shipped quantity and site |
Preserve the PO version, line and schedule above these rows. Give each milestone a named supplier contact, a buyer review time and a closure condition. “Sample done” is incomplete if the sample has not passed the agreed check or the report covers another drawing. Record “supplier reports complete” separately from “buyer or quality has reviewed the evidence.”
Oracle’s E-Business Suite 12.1 iSupplier order-information guide describes supplier deliverables with status reports and attachments when Procurement Contracts is implemented. That is one documented product mechanism. The worksheet here can also be maintained through a controlled spreadsheet and supplier correspondence, without implying those modules are installed.
Follow the fictional 18-bracket production lot
The fictional R-P26 warehouse pilot needs 24 BRK-260 Rev B brackets at US site AUS-01. Six are already accepted and reserved. PO-P26-018 version 1, line 10, orders the remaining 18 from invented Supplier M site M-01 on Tuesday December 1, 2026. An earlier qualification sample is retained for evaluation and contributes zero build stock. The supplier’s acknowledged production plan covers the same 18 ordered pieces.
The original target is usable material before the Monday December 14, 09:00 CST issue. The accepted dock commitment is Thursday December 10 at 09:00, with forecast usability Friday December 11 at 09:00 after one staffed working day for inspection and put-away. The receiving site works weekdays, has no closure in this original interval and has a 09:00 planning cutoff. All milestones and replies below are invented.
| Milestone | Original target | Evidence at Monday December 7, 15:00 CST | Current decision |
|---|---|---|---|
| Material and fixture ready | Thursday December 3, 15:00 | M-SETUP-01 identifies Rev B and the 18-piece lot | Supplier-reported setup reviewed |
| First-off check | Friday December 4, 15:00 | M-FIRST-01 covers the agreed Rev B characteristics | Quality accepts the sample evidence for process continuation |
| Final lot inspection and documents | Monday December 7, 15:00 | Final report not available for the 18 pieces | Missed milestone, buyer action due December 8 at noon |
| Dispatch | Wednesday December 9, 09:00 | Carrier collection not yet evidenced | Original dispatch remains at risk |
| Dock at AUS-01 | Thursday December 10, 09:00 | Future accepted commitment, not a receipt | Planner seeks current confirmation |
| Usable after receiving | Friday December 11, 09:00 | Future forecast conditional on acceptance | No new accepted stock at this snapshot |
The fixture and first-off checks do not add units to supply. The first-off piece is one of the ordered 18 and remains supplier WIP until shipment and receiving acceptance. An approved sample supports a production decision under the stated scope. It does not accept the entire lot or prove a future dock date.
Turn the missing inspection into a timed buyer decision
On December 8, Supplier M reports a finish-queue delay and proposes final inspection Tuesday December 15, dispatch Wednesday December 16 and dock Thursday December 17. The buyer retains that proposal beside version 1. The planner calculates forecast usability Friday December 18 at 09:00, four site working days after Monday’s planned material issue. The original PO date stays visible until the authorized purchasing change is accepted.
At the unchanged December 14 issue, six brackets support only 6 ÷ 2 = 3 complete bracket sets for this 12-robot build. The remaining nine sets need 18 more brackets. That is a line-level result, not permission to start three robots. The NPI owner must confirm the other materials, capacity and an approved split before using it.
| Response | Evidence the buyer needs | Material implication |
|---|---|---|
| Wait for proposed standard route | Accepted amended schedule, final inspection scope and transport slot | 18 forecast usable December 18, subject to receipt acceptance |
| Request an earlier route | Supplier capacity, matching inspection scope, new fee and carrier dates | Recalculate from the offered dock date, not “rush” status |
| Split the build using six accepted brackets | Complementary kit coverage and NPI-approved three-robot allocation | Nine robot bracket sets remain uncovered |
| Change drawing or accept an exception | Engineering and quality disposition for the exact affected lot | Keep outside compatible coverage until authorized |
Name the last useful decision time. Here the buyer must obtain the revised route and cost by December 8 at noon so the NPI lead can review alternatives while capacity is still available. If the supplier has not supplied that evidence, record the decision as unresolved and escalate. A recurring “checking with production” update should not close a missed milestone.
Translate dispatch into usability and close with actual events
Oracle’s purchase-order scheduling guidance distinguishes ship and delivery dates and considers transit and receiving calendars. In this teaching site, a confirmed Friday December 11 dock would become usable Monday December 14 because of the weekend. If that site instead closed Monday December 14, the same one-working-day receiving allowance would give Tuesday December 15. The closure example is a sensitivity, not a change to the main fixture.
po_id,po_version,line,schedule,part_id,drawing_revision,milestone_id,planned_completion,supplier_reported_completion,report_received_time,evidence_ref,reviewer,review_status,open_quantity,next_action,action_owner,decision_due,accepted_change_ref
Once dispatched, match the actual shipment to the PO schedule. Once received, record counted, accepted and held quantities in the receiving system. Do not mark the order complete because its last production milestone passed. The AI PO follow-up guide can consume a version-aware exception queue, and the clear-to-build guide recalculates material timing from accepted commitments and usable receipts.
Frequently asked questions
Does a supplier’s “in production” update prove the delivery date?
It establishes only the progress supported by that update. Ask which operation, quantity, revision and evidence it covers, then check the remaining finish, inspection and transport steps. Retain the accepted delivery commitment separately and reconfirm it when progress no longer supports it.
Should milestone quantities be added to ordered supply?
No. The fixture, sample and production rows describe the same 18-piece order. They create no additional incoming quantity or accepted stock. Count remaining PO schedules once, then reduce their open balance when actual receiving events enter the inventory record.
What should happen when a milestone is missed?
Record the missing evidence and the last useful decision time, then ask the supplier for the cause and feasible revised dates. Purchasing accepts commercial or schedule changes under the agreed process, engineering or quality reviews technical exceptions, and the planner recalculates the material effect. Keep the prior commitment recoverable.