When a robotics bill of materials (BOM) changes, check which builds need the new revision, then reconfirm the affected quotes and amend the affected purchase orders through their authorized owners. A released drawing does not rewrite a supplier's quote, cancel work already started or change an issued purchase order (PO). Preserve those records, establish the supplier's current work status and agree the revised scope, cost and dates before counting new-revision supply for the build.
Set effectivity before changing purchasing scope
Engineering identifies the accepted part and drawing revision, the change approval and the builds, serials or dates it covers. Record whether old-revision parts remain permitted for an earlier lot, need rework or require a separate disposition. A higher revision letter alone does not establish interchangeability.
For a custom bracket, provide the released drawing reference and its revision, material, finish and inspection requirements. For a catalog encoder, preserve the exact manufacturer and manufacturer part number (MPN). For a custom harness, preserve the harness and drawing revision. The buyer needs these different identities to request comparable quotes from a mixed robotics BOM.
A stable released reference matters even if engineering continues designing. Onshape distinguishes in-progress objects, pending release candidates and released revisions, with approval rules configured by the administrator. Check the actual release state and approver rather than treating the latest workspace as approved purchasing scope. Onshape release-management documentation.
The BOM revision and product configuration guide explains how a revision selection applies to a defined build. Use that selection to bound the affected buying lines.
Reconfirm the quote before reusing its price or lead time
Find every affected request for quotation (RFQ), supplier quote, purchasing request and open PO line. Retain the original RFQ package and quote version. Mark a quote that covers the old drawing as requiring reconfirmation for the new scope. Send the changed drawing identity, quantities, acceptance requirements and requested dock date, and ask for a replacement quote or an explicit scoped amendment to the existing one.
Compare offers only after the suppliers answer against the same release. A backup shop offering Rev C cannot be scored as an available Rev D source. Ask it to reconfirm Rev D manufacturability, setup, minimum quantity, unit price, inspection evidence and delivery basis. Keep exceptions visible beside the quoted terms.
| Record | What the change means | Owner's next action |
|---|---|---|
| Open RFQ | The supplier may be working from the previous drawing package. | Buyer issues an identified RFQ update and asks for readback. |
| Received quote | Its price, exclusions and lead time cover its stated scope. | Buyer requests reconfirmation before using it for the new revision. |
| Issued PO | Existing obligations remain recorded while the amendment is reviewed. | Buyer follows the agreed change process and keeps both versions. |
| Supplier WIP | Started work may carry cost or require technical disposition. | Engineering decides permitted use and buyer agrees the commercial treatment. |
Use the robotics BOM RFQ template to prepare the revised request. A request for a new quote is distinct from authorizing the supplier to make the changed part.
Reconcile receipts, supplier work in progress (WIP) and unstarted quantity
For each affected PO schedule, reconcile ordered, received, canceled and open quantities. Ask the supplier to split the open balance into completed parts, work in progress and unstarted parts, with its response date and operation stage. Keep supplier-held material separate from stock accepted at your site.
If a pause is needed, obtain an authorized instruction and record the supplier's acknowledgment. Engineering can continue work outside the affected release. Purchasing can continue unaffected lines. Old-revision parts can continue toward a specifically permitted earlier build. The disputed line needs its own disposition before further changed work is authorized.
Preserve the currently approved PO while reviewing its replacement. Oracle Cloud Procurement 26D keeps that approved version in effect for downstream activities until change-order approval, acceptance and validation are complete. Apply the equivalent controls in your purchasing system and the terms agreed with the supplier. Oracle Cloud Procurement change orders.
Join the release, quote and order with exact references
Use one change record that links to the authoritative sources. Do not maintain a second editable copy of each drawing, quote and PO. These fields let the receiver check that a commercial update belongs to the approved technical change.
| Joined record | Fields to retain | Receiver check |
|---|---|---|
| Build and release | Build ID, site, BOM release, line, required revision, quantity, unit and effectivity approval. | Engineering's selected revision applies to this lot. |
| Drawing package | Part or exact MPN, released file reference, drawing revision and inspection scope. | The file opens and its identity matches the request. |
| RFQ and quote | RFQ revision, supplier, quote ID/version, covered drawing, quantity, validity, price, exceptions and lead-time basis. | The supplier has quoted the changed scope. |
| PO and amendment | PO/version, line/schedule, original balance, proposed split, amendment approval and retained prior version. | Commercial approval preserves the authorized technical selection. |
| Supplier response | WIP statement, acknowledgment reference/time, accepted quantities, revision, terms and committed dock dates. | Scope acceptance and date commitment are recorded separately. |
| Disposition and coverage | Old-revision decision, owner, open question, due action and affected build shortage. | No unresolved quantity is counted as compatible, timely supply. |
Give missing or stale fields an owner and a next check. A quote outside its validity needs reconfirmation. An old WIP reply needs a current status. A broken drawing reference needs the released source. Keep the last accepted record visible while holding the affected candidate, and record which evidence will close the hold.
Worked example of a bracket change for 12 warehouse robots
This fictional example follows 12 warehouse robots at one receiving site. Each needs two BRK-140 Rev D brackets, one exact-MPN encoder and one WH-300 Rev B harness. Gross demand is 24 brackets, 12 encoders and 12 harnesses. Engineering has approved Rev D for this lot. Eight accepted Rev C brackets are reserved for an earlier lot and cannot cover these robots.
Before the change, supplier A's PO 4821 line 10 ordered 24 BRK-140 Rev C. Eight have been accepted at the site, four are in supplier WIP and 12 are untouched. The open balance is 24 minus 8 received, with no cancellations: 16. The buyer obtains a current WIP statement and revised quotation. Supplier A receives the released Rev D drawing package for its revised scope. Engineering's effectivity decision requires D for the new lot and leaves the four C pieces in WIP for a separate disposition.
| Original quantity | State | Approved action or open decision |
|---|---|---|
| 8 Rev C | Accepted at the site | Remain reserved for the earlier lot. |
| 4 Rev C | Supplier WIP | Separate technical and commercial disposition. Excluded from the D lot. |
| 12 Rev C | Unstarted | Buyer approves amendment converting these 12 to Rev D under revised terms. |
Keep the original order history and identify the new D schedule in the amended order. The four C pieces do not disappear from the open balance while their disposition is unresolved. They are also excluded from the new lot's material coverage.
Supplier B initially offers eight Rev C brackets. The buyer sends supplier B the released Rev D drawing package and asks it to requote against that scope. Only after D scope and commercial terms are accepted does the buyer order eight D. Its delivery date is still unconfirmed. The unchanged encoder and harness suppliers keep their current approved scope. The site already has four usable D brackets, so 4 in stock plus A's 12 and B's 8 would cover 24 if all incoming quantities arrive and pass acceptance. That arithmetic describes quantity coverage, not a committed issue date.
Approve the amendment and read back the supplier's response
The buyer's amendment records the converted quantity, retained WIP, exact drawing package, revised price and any agreed setup, rework, cancellation, inspection or freight charges. Engineering approves technical scope and disposition. Purchasing approves the commercial change. Receiving owns the inspection and stock-acceptance record. Keep each decision attributable.
Ask the supplier to read back the amended PO/version, line or schedule, revision, quantity and terms. Capture a committed dock date for each delivery split. A quote saying two weeks needs a stated starting event and an agreed date. Scope acceptance without a date leaves an open schedule question.
Under Oracle's specified document-and-schedule acknowledgment workflow, suppliers can propose price, quantity, delivery-date and schedule-split changes. The buying organization then reviews and approves the change. A supplier's proposed date remains a proposal until accepted through the applicable process. Oracle supplier acknowledgment.
If the reply omits D, references the old drawing, excludes required inspection or changes a term, hold that affected candidate and ask for a corrected response. Preserve the message and the buyer's decision with the order.
Recalculate coverage without turning an open date into a promise
By the Monday 7 December 2026 snapshot, six of A's 12 D brackets have been accepted into stock. With the four initially usable D, the site has 10. A's other six are confirmed to dock Wednesday 9 December and become usable Thursday 10 December after the example's inspection and put-away allowance. Only 16 of the required 24 D are forecast usable by the planned Friday 11 December issue.
B's eight D have no committed date, so there is no supported full-batch material issue date. The 12 encoders are usable after subtracting three reserved units from 15 physical units. Seven harnesses are accepted and five are confirmed usable on Thursday 10 December. That supports a candidate eight-robot lot on Thursday if the incoming parts pass inspection and the smaller lot is authorized.
Use the clear-to-build date calculation to follow the later B commitment and the cumulative supply. Use supplier-change acceptance when a source or process change also alters the evidence needed at receipt.
Questions about BOM changes, quotes and open POs
Does a released BOM revision automatically cancel an old quote or PO?
No. Retain the quote's original scope and ask the supplier to reconfirm the changed requirement. An issued PO needs its own agreed amendment or cancellation process. The released BOM supplies technical scope and effectivity, while purchasing records the commercial approval and supplier acceptance.
Can old-revision stock or supplier WIP cover the new build?
Only when engineering has explicitly permitted that revision for the build and the material meets its acceptance requirements. Here, Rev D is required for all 12 robots. The eight accepted C brackets remain reserved for the earlier lot, and the four C pieces in WIP need a separate disposition.
What if the supplier accepts Rev D but has not confirmed a delivery date?
Keep the D quantity as an open order and mark its date unconfirmed. Assign the buyer to obtain a commitment and escalate against the issue need-by date. Exclude it from dated full-batch coverage until the schedule is confirmed. A later committed receipt still needs inspection and put-away before material is usable.