Compare supplier quotes with AI by checking each offer against the same released scope, then normalizing quantity, price basis, tooling, freight, MOQ, validity and delivery status into a source-linked table. Gate wrong revisions and incomplete terms before ranking. The buyer reviews the comparison and approves an award separately, especially when the cheapest comparable offer has no confirmed delivery date.
This fictional example compares offers for eight BRK-140 Rev D brackets at one US site. Supplier B and supplier C, their prices and all December 2026 dates are synthetic. They are separate from the real candidate shops and distributors in the supplier guide.
Set one comparison basis
RFQ-WR-12-BRK-008-r1 requests 8 ea to released drawing DW-BRK-140-D-R1 and its matching STEP identity, aluminum 6061-T6 and clear anodize. Requested dock is December 9 at US-NPI-01. The comparison snapshot is December 4, 2026 at 10:00 a.m. PST. Both D offers are valid through that day. Each covers MOQ 8 ea, order multiple 1, Net 30 and one freight delivery to this dock. Sales tax is explicitly excluded and must be resolved separately.
The robotics quote-comparison method owns the broader commercial comparison. This guide adds a copyable AI prompt and traceable output from three different source representations.
Read the supplied source representations
The PDF name and workbook name below are synthetic labels. These examples are text excerpts and cells embedded in the teaching fixture. No PDF binary, scanned image or workbook file was parsed.
PDF excerpt: Q-B-D-r1, page 1.
L1 Fictional quote Q-B-D-r1 dated December 3, 2026. RFQ-WR-12-BRK-008-r1 acknowledged.
L2 BRK-140 Rev D, drawing DW-BRK-140-D-R1 and matching STEP. 8 ea. USD 72 per ea. Extended USD 576.
L3 One-time tooling USD 40. Freight to US-NPI-01 dock USD 24. Pre-tax total USD 640.
L4 MOQ 8 ea. Order multiple 1 ea. Net 30. Sales tax excluded. Valid through December 4, 2026.
L5 Requested December 9 dock has not been confirmed. No technical exceptions.Spreadsheet: Q-C-D-r1, sheet Quote. Cells B1–B3 identify Q-C-D-r1, RFQ-WR-12-BRK-008-r1 and BRK-140 Rev D to the released drawing, with matching STEP and no exceptions.
| Cell reference | Meaning | Value |
|---|---|---|
| Quote!B4:F4 | Quantity, unit, currency and price basis | 8 ea, USD 69 per ea |
| Quote!G4 | Extended item price | USD 552 |
| Quote!B6:B8 | Tooling, freight and pre-tax total | USD 100, USD 28, USD 680 |
| Quote!B9:B13 | MOQ, multiple, terms, validity and tax | 8 ea, 1 ea, Net 30, December 4, sales tax excluded |
| Quote!B14:B15 | Date and delivery basis | Dock unconfirmed, freight covers one delivery to US-NPI-01 |
Email: Q-B-C-r0, received December 2. This historical response was to the superseded C inquiry.
We can quote 8 BRK-140 Rev C at USD 55 per ea, MOQ 8 and order multiple 1. Tooling is USD 0 and freight to US-NPI-01 dock is USD 24. Net 30. Sales tax excluded. Valid through December 4, 2026. Delivery date is unconfirmed.
Copy the quote-comparison prompt
Normalize the embedded fictional PDF excerpt, spreadsheet cells and email to one evidence-linked comparison for RFQ-WR-12-BRK-008-r1 quantity 8 ea. Preserve quote version and source field locations. Gate revision, package, quantity, currency, units, MOQ, validity and cost completeness before ranking. Compare current matching offers by pre-tax total = quantity × per-ea price + tooling + delivered freight. Leave unconfirmed dates unconfirmed and route exceptions to the buyer. Do not award or create an order.
Rank current matching offers by comparable total
For this review, calculate pre-tax total = quantity × per-ea price + one-time tooling + freight. Rank current matching USD offers by that total, then quote ID if tied. Exclude missing cost terms and incompatible scope.
| Offer and scope | Item price | Tooling + freight | Pre-tax total | Review result |
|---|---|---|---|---|
| Q-B-D-r1 8 BRK-140 D | 8 × USD 72 = USD 576 | USD 40 + USD 24 | USD 640 | Cost rank 1. Dock unconfirmed |
| Q-C-D-r1 8 BRK-140 D | 8 × USD 69 = USD 552 | USD 100 + USD 28 | USD 680 | Cost rank 2. Dock unconfirmed |
| Q-B-C-r0 8 BRK-140 C | 8 × USD 55 = USD 440 | USD 0 + USD 24 | USD 464 | HOLD. Wrong revision and superseded RFQ |
C’s lower unit price produces a total USD 40 higher than B’s D offer. The cost ranking makes that trade visible. It supplies no timely-delivery commitment, and excluded sales tax does not mean zero payable tax.
Keep evidence pointers on normalized cells: B’s scope and unit price are SRC-Q-B-D-r1:p1:L1-L2, its tooling/freight are p1:L3 and its unresolved date is p1:L5. C’s price basis is SRC-Q-C-D-r1:Quote!B4:F4, tooling/freight are B6:B7 and its date is B14. The C-revision hold points to SRC-Q-B-C-r0:body:sentence1.
Hold a cheaper incompatible reply
Q-B-C-r0 cannot win this D request even though USD 464 is lower. Record the wrong-revision exception for engineering and ask the supplier for a current D offer. Preserve the C response as history. At a new December 7 award review, both December 4 D offers would also need renewed validity.
The buyer checks the selected drawing, quantity, units and original cost passages before using the ranking. An absent freight amount stays unknown, and a price per pack needs an explicit pack conversion. Review price and date changes in the approved purchasing process. Oracle Procurement 26D change-order documentation keeps the current approved version until change processing completes.
Carry the approved offer into PO tracking
Once a buyer approves an order, track the PO and supplier acknowledgment by version and schedule. The robotics AI procurement guide connects the source request, quote comparison and later material forecast.
Adjust a historical PO before using it as a reference
Use past orders as evidence only after matching the part and revision, site, currency, unit, lot size, date and included charges. The following separate fictional historical record is a cost reference, not a third WR-12 offer. Historical rates and normalizing assumptions are illustrative; they do not establish a supplier price or a statistically valid forecast.
| Input | Recorded or assumed value | Eight-piece comparison |
|---|---|---|
| Earlier PO | 20 matching Rev D brackets, USD 50 each; USD 100 one-time setup; freight excluded | USD 1,100 total for 20 |
| Current lot adjustment | Same USD 50 per unit assumed; new eight-piece setup USD 80; estimated freight USD 24 | 8 × 50 + 80 + 24 = USD 504 |
| Limits | Same site and revision assumed; prices are USD, so no FX conversion | Taxes and other differences remain open |
For a different currency, record the dated exchange rate and conversion basis before comparing; do not mix rates or treat missing freight as zero. Check inflation, material, tolerances and the current supplier’s tooling assumptions. A historical adjustment is an evidence-based benchmark, not the independently constructed should-cost model. Arc can normalize submitted unit prices and tooling charges for the buyer to review against both references; the buyer decides what to challenge and award.
Frequently asked questions
Can AI compare a PDF, spreadsheet and email quote?
It can help normalize readable source content when the chosen surface supports those inputs. This example uses supplied text, spreadsheet cells and an email excerpt. Check the actual original files and retain page or cell evidence. Binary parsing, image reading and extraction accuracy require a separate observed check in your intended tool.
Should I choose the lowest unit price?
Compare the complete commercial scope. Here C quotes USD 69 per ea versus B’s USD 72, but higher tooling and freight make C’s comparable pre-tax total USD 680 versus USD 640. Delivery is unconfirmed for both, so cost rank alone cannot establish the build’s timely supply.
Can I rank a quote for an older drawing revision?
Hold an offer whose revision differs from the released request. Keep it identifiable for engineering disposition and obtain a current matching reply. A lower cost or unchanged total quantity does not approve Rev C for WR-12’s Rev D requirement.