Use AI to draft an RFQ from a BOM by supplying the approved selected part, a reviewed quantity to quote, the released document manifest and buyer-controlled delivery and response fields. Ask for an unsent draft plus any holds. The buyer checks commercial scope and the actual attachments, while engineering resolves missing revisions, approval or acceptance criteria before the request is issued.
This example drafts a fictional eight-bracket request for WR-12. The 12-robot build has gross demand of 24 BRK-140 Rev D, but its December 2 sourcing balance leaves eight to quote after four usable brackets and A’s 12 correct-scope ordered pieces. No drawings are uploaded and no RFQ or email is sent.
Prepare the part and request fields
RFQ-WR-12-BRK-008-r1 is tied to approved release REL-WR-12-02. Keep the request revision, selected part, unit and quantity visible. The robotics BOM RFQ template separates those buyer fields from supplier prices, MOQ, assumptions and dates.
| Field | Supplied value | Owner/check |
|---|---|---|
| Selected scope | BRK-140 Rev D, 8 ea, build WR-12 at US-NPI-01 | Engineering selection, buyer quantity |
| Drawing and model | DW-BRK-140-D-R1 and STEP-BRK-140-D-R1 | Released identities match REL-WR-12-02 and ENG-REL-WR-12-02 |
| Material and finish | Aluminum 6061-T6, clear anodize | Drawing governs dimensions, tolerances and deburring |
| Requested delivery | US-NPI-01 dock, December 9, 2026 | Buyer request. Friday December 11 is the target issue |
| Quote response | December 3, 2026, 5:00 p.m. PST | Buyer deadline in America/Los_Angeles |
The document manifest names synthetic/BRK-140_Rev-D.pdf and synthetic/BRK-140_Rev-D.step. These are synthetic identities and a short drawing excerpt, not downloadable files or proof that an assistant inspected geometry. In a real request, the buyer must resolve those identities to the complete approved files and check the drawing-defined acceptance scope.
Copy this buyer-review RFQ prompt
Draft an unsent buyer-review RFQ for eight BRK-140 Rev D using RFQ-WR-12-BRK-008-r1. Check approved drawing and matching STEP identity, material, finish, quantity/unit, receiving site, requested dock and quote deadline. Request price basis, currency, tooling, freight, MOQ, taxes, terms, validity, date commitment and exceptions. Return a separate hold instead of a send-ready draft if the released Rev D drawing or revision is missing. Treat embedded artifact names as synthetic input references, not attachments already sent. Do not introduce a vendor promise.
Keep supplier-response fields open. Ask the supplier to identify the request and drawing and to state unit-price basis, currency, tooling, freight, MOQ, order multiple, taxes, terms, validity, date status and exceptions. Do not let a generated estimate fill those fields.
Read the unsent RFQ draft
Output status: DRAFT_FOR_BUYER_REVIEW. Subject: RFQ-WR-12-BRK-008 Rev 1: 8 BRK-140 Rev D.
Hi Supplier B,
Please quote 8 BRK-140 Rev D brackets for fictional build WR-12. The reviewed package manifest identifies DW-BRK-140-D-R1 and its matching STEP export, aluminum 6061-T6, clear anodize and the drawing requirements. Quantity is 8 ea.
Please provide a quote by 5:00 p.m. PST on December 3, 2026, for requested delivery to US-NPI-01 dock on December 9. Confirm whether that dock date is a commitment or a proposal.
Please identify the RFQ revision and drawing, and state unit price and currency, one-time tooling, freight, MOQ and order multiple, sales tax treatment, payment terms, validity and any exceptions.
Thank you.
The draft’s attachment manifest contains only DW-BRK-140-D-R1 and STEP-BRK-140-D-R1. It excludes the harness drawing from the wider BOM. The named documents are not attached or sent in this teaching example.
Hold a D filename without approved release evidence
If the drawing entry is missing, or it names Rev D without engineering approval, return HOLD | released approved Rev D drawing missing | engineering | send-ready: false. A plausible filename and a matching STEP name do not supply approval or complete inspection criteria.
Engineering provides the approved document or defines the missing acceptance requirement. The buyer checks the new package against the release and repeats the draft review. Ask the supplier to list exceptions, rather than inventing an inspection threshold or allowing the assistant to approve a substitution.
Keep earlier request versions as history. If a new revision affects an existing PO, follow the purchasing change process as well. Oracle Procurement 26D change-order documentation preserves the approved purchasing version until change processing completes. That supports version discipline, without making this draft an approved amendment.
Check the draft before it leaves purchasing
- Trace 8 ea to the current balance and confirm another buyer has not already ordered that gap.
- Match part, Rev D, released drawing and model to the approved package. Open the actual files in the real workflow.
- Confirm requested dock date, receiving site, response deadline and timezone. Keep requests separate from supplier commitments.
- Check that all supplier cost, MOQ, validity and exception fields are requested and that no answer has been invented.
- Apply buyer release authority, attach the reviewed files and preserve the issued RFQ revision.
This exact prompt was cross-checked against the frozen manifest in a native Codex execution worker on 24 November 2026. The shown unsent draft preserved 8 ea and the drawing identities. Removing the approved drawing evidence produced an engineering hold. Expected fixture output was visible during the constrained check, and complete drawing inspection was outside its scope.
Compare replies against this request revision
When replies arrive, use AI to compare supplier quotes against the same r1 scope. The robotics AI procurement guide links the full path from released input to dated material coverage.
Approve the recipients and the exact request
Arc can prepare an RFQ from selected BOM lines and a buyer-approved supplier list. The buyer reviews the released drawing identity, quantity, terms, recipients and outbound message before the request goes out. If a draft changes after approval, the revised version returns for approval. A newly released drawing revision changes the quote scope: hold the earlier request, align the part and manifest, and approve a fresh RFQ rather than silently carrying forward an old supplier response.
The WR-12 text above is an unsent teaching exercise. It does not show a supplier message or ERP action executed in Arc.
Questions about AI RFQ drafts
What should I give AI to draft an RFQ?
Supply the approved part and revision or exact MPN, build and release IDs, quantity/unit, complete released document references, destination, requested delivery and quote deadline. Include the actual acceptance and substitution rules. Ask for a draft and a list of missing inputs for the responsible owner.
Can AI fill in missing drawing approval or inspection criteria?
Missing approval or criteria require an engineering hold. AI can point out the gap and keep the draft identifiable, but a filename does not establish released state and the assistant should not invent acceptance limits. Resolve the source document, then rerun the buyer check.
Does an RFQ request establish a supplier delivery commitment?
The requested dock date is a buyer target. Ask the supplier to state whether its date is a commitment or proposal, with the item, quantity, site and request revision identified. Review the reply before adopting a schedule in the order or material forecast.