Bring a selected printing job in house when enough accepted parts can repay the fixed cost and the team can reserve the printer, operator and inspection time. Outsource when the service can meet the agreed part requirements and usable date more economically, or when internal capacity is occupied. A mixed plan can cover urgent or overflow work.
Compare the same drawing, material, process and acceptance scope. The rapid-prototyping guide owns the earlier choice among printing, machining and sheet metal.
Compare one accepted cover on both routes
This fictional job is COV-P24 B, a civilian robot's connector-access cover. Both routes use FFF printing, the same specified ASA filament grade and the released orientation/settings record. Its purpose is fit evaluation. Loaded service and protective performance remain outside its permitted use.
Both routes must deliver the finished drawing revision, mounting centres at 80.00 ± 0.30 mm, an assembled cable-access check and the inspection record. These limits are invented project requirements. Agree any material or process equivalent with engineering before comparing its price.
Formlabs' cost guide separates equipment, material and labour. Its SLS whitepaper includes printing, cooling, processing and delivery in vendor examples. Use those categories with your own process and rates. Their savings and times are specific to the published builds. Cost guide · SLS comparison method
Price attempts and accepted parts separately
All GBP figures below are fictional planning inputs. Internal yield is initially 80%, meaning eight accepted covers per ten attempts under the specified settings. Every attempted cover consumes eight printer hours. Yield must include the drawing and fit checks.
| Internal cost | Model input |
|---|---|
| Installed equipment, setup and training | £6,000, annualised over three years with zero residual value |
| Annual service and calibration | £600 |
| Annual fixed allocation to this job | £6,000 / 3 + £600 = £2,600 |
| Material per attempt | £5 |
| Energy and consumables per attempt | £1 |
| Hands-on preparation, finishing and inspection per attempt | 0.50 hours × £36 loaded labour/hour = £18 |
| Total per attempt | £24 |
The £36 rate includes employment and overhead loading. Printer run time and hands-on labour are separate inputs. Finishing and inspection include failed attempts in this model.
The service's fictional quote is £42 per accepted cover, including its printing, finishing and yield losses. Add £3.60 for internal receipt inspection and £2.40 allocated freight per accepted cover. Comparable outsourced cost is £48. Freight allocation assumes the quoted lot pattern.
Both totals exclude tax, financing and common design work. If a real offer changes lot size, inspection or freight, update the comparison. Count each loss, labour task and fixed allocation once.
Calculate the whole-unit crossover
Let n be annual accepted demand and y the conditioned acceptance yield. Round planned attempts up to a whole number.
attempts = ceil(n / y)
internal annual cost, GBP = 2,600 + 24 × attempts
outsourced annual cost, GBP = 48 × n
| Accepted annual demand | Attempts at 80% | Internal total | Outsourced total |
|---|---|---|---|
| 100 | 125 | £5,600 | £4,800 |
| 145 | 182 | £6,968 | £6,960 |
| 146 | 183 | £6,992 | £7,008 |
| 300 | 375 | £11,600 | £14,400 |
The continuous approximation gives £2,600 / (£48 − £24/0.8) = 144.44 accepted parts. Whole-attempt rounding makes 146 the first cheaper internal quantity in this model.
| Conditioned yield | First cheaper internal quantity |
|---|---|
| 100% | 109 accepted parts |
| 80% | 146 accepted parts |
| 60% | 327 accepted parts |
Attempts are a planning estimate, with actual acceptance still to record. Recalculate after a representative print trial. Low demand or lower yield can reverse the apparent saving.
Check hours before buying capacity
At 300 accepted covers, 375 attempts need 3,000 printer hours. If only 2,200 hours remain after maintenance and other committed jobs, the all-internal plan is infeasible.
That capacity supports 275 attempts, or 220 accepted covers at the modelled yield. Printing those internally costs £2,600 + 275 × £24 = £9,200. Outsourcing the other 80 costs £3,840, giving a mixed total of £13,040. That is £1,360 below all-outsourced cost under the same assumptions.
For a printer already owned, compare avoidable costs for the new decision. Past purchase expenditure is sunk. Retain additional service, tooling, labour and consumables that the job actually causes. Also account for the work displaced from its reserved hours. Do not use the annual acquisition model unchanged for one small job.
Plan the date of usable parts
A fictional ten-cover lot is needed by Friday 4 December 2026 at 16.00 GMT. The released files are ready Monday 30 November at 09.00 GMT.
| Route | Capacity and production inputs | Earliest planned usable lot |
|---|---|---|
| Internal | Sixteen hours of existing queue, then 13 planned attempts × eight hours. Even continuous machine operation needs at least 120 elapsed hours. | Printing completes no earlier than Saturday 5 December at 09.00 GMT. Staffed final finishing/inspection is reserved Monday 7 December by 10.00 GMT. |
| Service | Supplier confirms the exact finished scope and Thursday 3 December arrival at 09.00 GMT. Internal receipt checks have a reserved slot. | Thursday 3 December at 12.00 GMT, conditional on accepted receipts. |
The internal date is a lower-bound schedule plus the stated staffed acceptance slot. Changeovers, failed extra attempts or operator gaps can move it later. The fictional service commitment can meet this lot's date, with actual acceptance required. The annual cost result alone cannot authorise the urgent internal route.
Before award, record the accepted part identity, quantity, yield basis, allocated fixed cost, planned attempts, reserved machine/operator hours, quote inclusions and usable date. Use the five-robot sourcing guide and Bay Area printing category to prepare an equivalent supplier enquiry.