An incoming inspection checklist for a small CNC lot should identify the parts received, the applicable drawing revision and the checks required before issue. Record counted, inspected, accepted and quarantined quantities separately. Keep measured results, equipment references and the release owner with the receipt so manufacturing can see the usable quantity.
Start with the drawing and order requirements
Check the PO, received labels and lot identity against the released part. Retrieve the dimensioned drawing and any agreed inspection plan, including material, finish, thread checks and fit-critical features. Record the promised documents and confirm that each report covers the actual lot and revision.
The inspection scope comes from your drawing, order and risk assessment. Xometry’s published options distinguish standard checks from formal dimensional reports and custom inspection. Agree the report and sampling scope before ordering when the receipt decision needs that evidence. Xometry inspection options.
A supplier report can support the receiving decision. The receiving owner still checks its identity, coverage and any gaps in the agreed acceptance scope. A declaration of the material grade should be backed by the required certificate or traceability record when your order calls for it.
Copy the receiving and measurement records
Copy these blank tables into the lot record. Add a row for each required characteristic and a reference to the measurement method. Record unused fields as not applicable with a reason.
| Check or field | Evidence or result | Owner and status |
|---|---|---|
| PO version, line, supplier and receiving site | ||
| Part number, drawing revision and lot or serial identity | ||
| Expected quantity and counted quantity | ||
| Packing slip and required material or finish records | ||
| Damage, deburring, finish and cleanliness checks | ||
| Inspection plan, drawing characteristics and method | ||
| Gauge identity, calibration status and measurement conditions | ||
| Inspected, accepted and quarantined quantities | ||
| Accepted location, hold location and nonconformance reference | ||
| Release decision, reviewer and date |
| Item identity | Drawing characteristic and limit | Method or gauge | Measured result | Disposition and reviewer |
|---|---|---|---|---|
Choose a method capable of deciding the stated characteristic. A handheld calliper reading does not establish a geometric position tolerance referenced to a datum scheme. Ask the quality owner to define the fixture, measurement uncertainty and decision rule needed for the actual drawing.
NIST describes metrological traceability through a documented calibration chain and explains that traceability alone does not guarantee fitness for purpose. Retain the measurement capability evidence needed for your limit. NIST metrological traceability policy.
Inspect five illustrative Rev C brackets
The fictional civilian R-PILOT build needs five BRK-101 Rev C sensor-support brackets, one per robot. Receipt RCPT-101 contains five from lot LOT-C101. This teaching inspection checks all five against its agreed plan. Four pass and one is quarantined. The part limits, measurements, gauges and decisions below are illustrative and establish no universal CNC tolerance.
Teaching drawing DWG-BRK-101 Rev C identifies C1 as a locating boss diameter of 10.00 mm ± 0.05 mm, an acceptable interval of 9.95–10.05 mm. C2 is a mounting thickness of 6.00 mm ± 0.10 mm, an interval of 5.90–6.10 mm. Micrometers MIC-01 and MIC-02 are assumed suitable, with valid calibration records and a reviewed measurement decision rule. The example measurements sit clearly inside or outside the limits.
| Bracket identity | C1 boss diameter, MIC-01 | C2 thickness, MIC-02 | Other agreed checks | Quality decision |
|---|---|---|---|---|
| B101-01 | 10.00 mm | 6.02 mm | Pass | Accepted |
| B101-02 | 9.99 mm | 6.01 mm | Pass | Accepted |
| B101-03 | 10.02 mm | 5.99 mm | Pass | Accepted |
| B101-04 | 10.01 mm | 6.03 mm | Pass | Accepted |
| B101-05 | 10.20 mm | 6.00 mm | Other checks pass | Quarantined for C1 |
“Other agreed checks” in this exercise covers identity, receipt documents, the specified material and finish evidence, deburring, damage and the drawing’s remaining required features. Their underlying results belong in IR-101. The two numeric columns show selected characteristics only. A real record needs every check called for by the agreed inspection plan.
| Record field | Worked result |
|---|---|
| Counted and inspected | 5 counted and 5 inspected under IR-101 |
| Accepted and quarantined | 4 accepted and 1 quarantined, so 4 + 1 = 5 |
| Accepted material location | R-PILOT kit shelf K-01, identities B101-01 through B101-04 |
| Hold identity and location | B101-05 in labelled quarantine bin Q-01, NCR-101 |
| Measurement record | IR-101 with MIC-01 and MIC-02 calibration references and inspection conditions |
| Release owner | Named supplier-quality owner signs the four-unit release and one-unit hold |
Release the accepted quantity and contain the failure
Keep the quarantined bracket physically identified and blocked from issue. The quality owner assesses whether the failure could affect the other four, related lots or the selected measurement method before releasing the accepted subset. Preserve the failed result, drawing requirement and containment decision in the supplier nonconformance report.
In this exercise, the review supports releasing four. With no other accepted stock, five required − four accepted = one bracket short. Record that shortfall in the pilot-build readiness checklist. Count a replacement only after it arrives and passes the required checks.
Arc’s published BOM and revision workflow links the selected part and drawing references for review. In a demo, use the receipt and hold as evidence references and inspect which build records the bracket question affects.
Questions about incoming CNC inspection
Should we inspect every part in a five-piece CNC lot?
Choose the scope through the agreed inspection plan and the part’s risk. This example inspects all five and records individual results. A small lot alone does not prescribe a universal sampling rule or establish that two measured dimensions cover the full drawing.
Does a supplier dimensional report replace our incoming check?
The receiving owner should verify the report’s part, revision, lot, method and scope against the order. Use it as evidence where it covers the agreed checks, and resolve missing characteristics, damage or identity questions before releasing material.
How should we handle a result close to a drawing limit?
Apply the approved measurement method and decision rule, including relevant uncertainty. Escalate an inconclusive result to the quality owner, retain the readings and hold the affected item until the owner has enough evidence to decide.