A supplier nonconformance report should start with the failed requirement and the evidence from incoming inspection. Identify and contain the affected material, agree an authorised disposition with the supplier and retain the replacement or rework checks. Record who can close the occurrence and whether a separate corrective-action investigation remains open.
Write the failed check so it can be investigated
Use the part, revision, lot or serial, order line and measured result from the incoming CNC inspection record. State the required limit and the observed result. Keep photographs, gauge references and report versions with the occurrence. Avoid guessing the root cause from the symptom.
The fictional civilian R-PILOT receipt contains five BRK-101 Rev C brackets. Inspection IR-101 measures the locating boss on B101-05 at 10.20 mm against teaching characteristic C1, 10.00 mm ± 0.05 mm. The upper limit is 10.05 mm, so the reading exceeds it by 0.15 mm. These limits, measurements and records are illustrative.
Four brackets pass the agreed plan. The quality owner reviews the scope of the failure before deciding that the accepted four can be released and B101-05 must remain quarantined. The occurrence is NCR-101, linked to lot LOT-C101 and receipt RCPT-101.
Copy a supplier nonconformance report
Copy the blank record below. Keep the initial finding and subsequent decisions in dated entries so a later change cannot overwrite what was first observed.
| Field | Record or evidence reference | Owner and status |
|---|---|---|
| NCR identity, date and reporter | ||
| Supplier, site, PO version, line and receipt | ||
| Part, drawing revision, lot and affected item identities | ||
| Required characteristic, observed result and evidence | ||
| Counted, inspected, accepted and held quantities | ||
| Containment location and related stock or build review | ||
| Immediate build effect and recovery owner | ||
| Supplier response and response deadline | ||
| Authorised disposition and technical approval | ||
| Return authorisation, shipment and supplier receipt | ||
| Credit, replacement or rework commercial agreement | ||
| Replacement identity, arrival and reinspection | ||
| Corrective-action reference and effectiveness evidence | ||
| Occurrence closure evidence, owner and date |
Contain the affected scope before selecting a recovery
Label the held item with its NCR and keep it outside the assembly kit. Record whether the same drawing feature, supplier lot, process or measurement method could affect other received stock, work in progress or installed units. Assign each uncertainty to an owner. Release an unaffected subset only when the responsible quality review supports that boundary.
In the worked example, B101-05 is held in quarantine bin Q-01. The four accepted items are B101-01 through B101-04 on kit shelf K-01. The example assumes the scope review confirms those four meet the agreed requirements and no related stock exists. Without another accepted bracket, the five-robot demand is one unit short.
Agree a disposition through the team’s quality and purchasing authority. Options may include supplier replacement, authorised rework with defined reinspection, return for credit or an engineering-approved concession with exact effectivity. Record the approval and commercial agreement that apply. A supplier’s proposed rework needs review before the team uses the part.
Work the return and replacement through receipt
The following invented sequence continues NCR-101. It assumes discovery on Wednesday 2 December 2026 and planned material issue on Thursday 3 December. The supplier agrees to replace one bracket and provides return authorisation RMA-101.
| Step | Quantity and evidence | Owner decision |
|---|---|---|
| Contain failed receipt | 5 inspected, 4 accepted and B101-05 held | Quality records the scope review and one-unit shortage |
| Agree supplier disposition | RMA-101 covers return of B101-05 and one Rev C replacement | Buyer records freight, charges and replacement terms |
| Return the failed bracket | One dispatched under RMA-101 with supplier receipt readback | Receiving retains the shipment and NCR identity |
| Replacement arrives Friday 4 December | B101-R1 from replacement lot LOT-C102, received quantity 1 | Receiving routes it to reinspection before issue |
| Reinspect the replacement | C1 is 10.01 mm, C2 is 6.02 mm, and remaining agreed checks pass in IR-101R | Quality accepts one replacement against Rev C |
| Reconcile the occurrence | 4 original accepted + 1 replacement accepted = 5 usable brackets | Quality closes the item occurrence after return and receipt evidence are complete |
The original receiving record remains five counted, four accepted and one rejected for return. The replacement is a separate receipt of one. Counting all physical receipt events gives six arrivals over the recovery, with one returned and five accepted for use. Keep the returned item outside the usable total.
The fifth usable bracket becomes available on Friday, after Thursday’s issue. Close the material recovery with the actual date, and retain the original shortage and schedule decision. The pilot-build readiness record should show when the affected operation can proceed.
Keep occurrence closure and corrective action separate
Returning the failed item and accepting its replacement resolves this material occurrence. A corrective action addresses the verified cause and whether the change prevents recurrence. ASQ describes root cause analysis as a way to uncover causes within a wider problem-solving effort. ASQ root cause analysis.
Decide whether a formal corrective action is needed from the failure’s risk, repetition and contractual obligations. In this exercise, CA-101 remains open because the process cause has not been established. The quality owner records the supplier’s investigation scope, required evidence and next review. No root cause or successful process improvement is invented.
If corrective action is required, closure needs the agreed cause evidence, implemented action and effectiveness check. Give it a closure owner and keep it open independently of the five-bracket recovery.
Arc’s published engineering review workflow links part revisions, supporting evidence and proposed product changes for human review. Use the failed drawing characteristic and affected build references in a demo, then agree which quality and purchasing records remain authoritative.
Questions about supplier nonconformance reports
Can we release the four passing brackets while one is quarantined?
The quality owner can release the accepted subset when the scope review supports it under the agreed procedure. Identify the four released items and the held item, and check for a shared process or measurement issue that could affect the claimed passing results.
Does a replacement close the corrective action?
A checked replacement can close the material recovery or individual occurrence when its required evidence is complete. Corrective action remains open until the cause, implemented action and agreed effectiveness check support closure by its owner.
Who can approve rework or use of a nonconforming part?
Use the authority defined by your engineering, quality and purchasing procedures. Record the disposition, covered identities and any concession conditions, then define the reinspection needed before use. A supplier proposal alone provides no internal technical release.