Resolve a long-lead part shortage against the selected revision, affected serials and material-issue time. Give each response an owner and the evidence that makes it executable. Reserve time for receipt checks before allocation. If faster supply or an approved alternative remains unresolved at the decision point, issue the covered serials only within their accepted scope and hold the affected later unit.
The useful decision says which robot can receive which part, when it can be issued and what happens to the existing order. A supplier opportunity or a newer revision cannot fill those fields by implication. The MRP guide covers the underlying dated demand and supply calculation. This guide follows one shortage through the actual choice of action.
Identify the one uncovered serial
The fictional R-01 pilot selects HR-300 A with DW-HR-300 A for 001–002 and HR-300 B with DW-HR-300 B for 003–005. ECO-017 approves B's strain-relief manufacturing improvement while retaining the installation interfaces and acceptance requirements. Common selections remain DW-R01 A, ECAD CB-200 A and firmware 1.2.0. R-01 configuration matrix
This is a separate planning snapshot, L0, on 2027-01-11 at a fictional West Coast shop. All fixture times use Pacific Standard Time, UTC−8. The required release package and instructions are assumed accepted after the earlier packaging and readiness exercises. Every stock quantity, date, order and decision below is fictional. Shop staffing and all other material and assembly prerequisites are assumed available for the stated scope. The example establishes no real supplier cutoff or shop calendar.
| Planned serials | Selected harness | Material at L0 | Issue status to resolve |
|---|---|---|---|
| 001–002 | HR-300 A | Two accepted A harnesses allocated to these serials | Preserve the A allocation. |
| 003–004 | HR-300 B | Two accepted B harnesses allocated to these serials | Covered for the planned issue, subject to final readiness confirmation. |
| 005 | HR-300 B | One B remains on open order PO-HB-01 | Uncovered at the first issue date. |
The late order is for one complete HR-300 B harness to DW-HR-300 B. The supplier-stated warehouse arrival in the fixture is 2027-01-19 at 12.00 PST. That is a planning input, with physical receipt and acceptance still pending. The first issue is 2027-01-15 at 09.00 PST.
This January 15 issue time is a new illustrative planning event. The RFQ template's January 15 need-by date is an example request field. It supplies no delivery commitment and cannot establish that the harness is usable at the issue time. BOM RFQ template
Reserve receipt-check time before the last decision
The materials and quality owners reserve one staffed working day after warehouse arrival for identity, document and required receipt checks in this exercise. A real allowance depends on the actual part and process. The receiving team must confirm it before the planner uses a supplier arrival date.
For the 2027-01-15 issue, the latest acceptable warehouse arrival is 2027-01-13 at 12.00 PST. Receipt checks are scheduled for January 14, with material status reviewed by 16.00 PST. The last decision point is January 12 at 16.00 PST, allowing the buyer and build lead to secure the receipt plan or issue the split instruction before the cutoff.
| Milestone in L0 | Time | Required owner confirmation |
|---|---|---|
| Choose faster supply or the split branch | 2027-01-12 at 16.00 PST | Buyer and build lead identify the executable option and affected serials. |
| Latest warehouse arrival for first issue | 2027-01-13 at 12.00 PST | Buyer confirms actual delivery scope and receiving team confirms access. |
| Receipt checks and usable-status review | 2027-01-14, complete by 16.00 PST | Materials and quality owners record accepted identity, documents and allocation. |
| First material issue | 2027-01-15 at 09.00 PST | Release authority confirms permitted serials and operations. |
These times define a decision window for this fixture. Arrival by the cutoff still needs a passing receipt disposition. If checks reveal a mismatch or remain incomplete, the harness cannot supply the January 15 allocation.
Compare the branches and their approval needs
Keep candidate actions identifiable until their evidence exists. A supplier's shorter lead time is an offered plan. An alternate source is a proposed buying route. The build lead decides the permitted scope after engineering and receiving owners resolve the relevant conditions.
| Branch | Owner and affected scope | What makes it executable | State at the L0 decision | Existing-order consequence |
|---|---|---|---|---|
| Expedite PO-HB-01 | Buyer, one HR-300 B for 005 | Supplier confirms warehouse arrival by January 13 noon, unchanged drawing scope, terms and receiving capacity | Pending, no confirmed faster date in this scenario | Amend the same order and retain one open quantity, with the accepted new date. |
| Exact alternate source | Buyer with engineering and supplier-quality owners, one B for 005 | Exact item/drawing scope and source approval, required evidence, a feasible arrival and receipt plan | Hypothetical candidate, approval and supply unresolved | If replacing supply, reconcile PO-HB-01 through confirmed cancellation, reduction or an explicit extra-stock disposition. |
| Different item or revision | Engineering owner, one explicitly scoped candidate for 005 | Reviewed compatibility, affected evidence, exception or change approval and executable receipt plan | Pending proposal, unavailable for issue | Preserve the B requirement until the changed selection is authorised, then reconcile the original order. |
| Split harness issue | Build lead, 001–004 proceed within accepted scope and 005 held | Revision-specific allocations, accepted instructions and authorised split record | Defensible branch from the stated accepted quantities | Keep PO-HB-01's one B linked to 005 and the later issue plan. |
| Hold all affected work | Release authority, defined operations and serials | An explicit hold where common prerequisites prevent a bounded split | Available if the split cannot be authorised | Keep the late order visible while its disposition and restart conditions are resolved. |
An exact alternative source still needs source and receiving acceptance. A different harness revision additionally needs the engineering decision that changes or exceptionally permits the selection. The supplier-change acceptance guide provides the detailed evidence bridge for that decision.
The two A harnesses are allocated to 001–002. They cannot also cover 005, and the unchanged installation interfaces do not authorise using A in its B selection. Retain the revision identity throughout purchasing, receipt and issue.
Record the bounded split decision
At L1, the January 12 decision point, this fictional scenario still has no accepted expedite commitment or alternative approval. The release authority records SPLIT-R01-01 for harness issue to 001–004 under their respective A/B packages. Serial 005's harness issue and dependent work remain held under HOLD-005-01.
The materials lead preserves two A allocations for 001–002 and two B allocations for 003–004. The buyer keeps the one B on PO-HB-01 allocated to the later 005 requirement. No bridge order is added, and no later receipt is counted in the January 15 issue.
For the later branch, the January 19 noon arrival supports a proposed January 21 at 09.00 PST issue after January 20 receipt checks. Staffing for those local working days is assumed in the fixture. That later issue remains conditional on actual arrival, accepted material and the release authority's restart decision. The planner checks the remaining assembly capacity separately before promising completion.
The restart record should contain the actual received HR-300 B identity, DW-HR-300 B documentation, receipt acceptance, allocation to 005 and the accepted instruction scope. Record the installed revision later in the robot build record. The readiness checklist defines the bounded permission to resume work.
Keep future sourcing separate from immediate coverage
Investigate long-term alternatives early enough to inspect them. NIST MEP's Supplier Scouting process helps identify US manufacturers with specified capabilities and directs companies to an MEP Center. That supports a sourcing search. It provides no approval of the R-01 harness, delivery promise or closure of this week's shortage. NIST MEP Supplier Scouting
Keep product lifecycle status and dated supply in separate fields. TI, for example, documents lifecycle categories such as Active, NRND and Last Time Buy. Its inventory documentation separately identifies estimated future quantities and dates as forecasts. These semiconductor sources illustrate the distinction and supply no harness availability evidence. TI product lifecycle policy and inventory documentation
For each sourcing opportunity, retain the exact part/drawing, proposed source, quote scope, earliest credible receipt, approval owner and unresolved evidence. Keep the opportunity out of executable supply until those conditions are accepted.
Long-lead pilot-build questions
Can a late purchase order cover the first issue because its quantity is enough?
Its usable receipt must precede the issue. PO-HB-01 supplies the later 005 plan in this example and contributes zero to the first issue's B coverage.
What makes an alternate approved for use?
The authorised review must identify its item, revision, source, applicable robot scope and conditions. Receipt and build readiness still need their own checks.
Should a bridge order be added immediately?
First reconcile it with the existing order. Record whether the old supply is reduced, cancelled or deliberately retained as additional stock, with the buyer's decision and supplier acknowledgment.
Why split when expediting might work?
At the last decision point, the scenario has accepted material for 001–004 and no confirmed faster supply for 005. The bounded split uses the available evidence while preserving the later requirement and hold.
Continue the shortage review
Use the MRP guide for dated netting and the RFQ template for comparable supplier scope. Use the supplier-change guide when an alternative changes the engineering acceptance question.