Build a technical review action closure matrix

Use Arc Skills to check whether technical review actions have actually resolved the concern they were raised to address. The closure matrix connects each action to its required outcome, submitted revision, evidence quality and recorded reviewer disposition.

Use this skill

Use Arc Skills to build a technical review action closure matrix.

Inputs:
- Original action IDs, findings and closure criteria
- Submitted evidence with revisions and dates
- Recorded reviewer decisions and dependent actions

Return action, required outcome, evidence, adequacy finding, status, owner and next decision. Separate owner-reported completion from reviewer acceptance. Flag evidence that documents activity without resolving the concern.

Set up the toolkit · Read the skill instructions

What you provide and what you get

Inputs and outputs
What you haveHow it is usedWhat you get
Review findings and closure criteriaRecover the outcome each action must achieveAn auditable closure denominator
Submitted artifacts and exact revisionsCheck the concern against evidenceAdequate, incomplete and mismatched submissions
Reviewer decisions and dependenciesPreserve actual authority and re-opened effectsA decision-ready closure matrix

Three actions marked done, only one accepted

Illustrative engineering example.

A review tracker shows all three actions complete. Checking the evidence and decisions reveals different actual positions.

ACT-01: demonstrate connector pinout compatibility; owner attaches meeting minutes only.
ACT-02: close sensor calibration gap; CAL-07 rev B and matching serial number submitted; reviewer acceptance recorded.
ACT-03: correct throughput test; owner submits TEST-09 rev B with 4 messages/s criterion although INT-09 B requires 5.
Three actions marked done, only one accepted
ActionRequired outcomeSubmitted evidenceClosure findingNext action / authority
ACT-01Compatible controlled pinoutsMeeting minutes, no pin comparisonOpen: discussion does not establish compatibilityInterface owner submits signed pin table; reviewer assesses it
ACT-02Calibration for installed sensorCAL-07 B, matching serial, reviewer decisionAccepted by recorded reviewerRetain evidence and decision locators
ACT-03Procedure checks current 5 messages/s contractTEST-09 B checks 4 messages/sNeeds rework: wrong acceptance basisVerification owner corrects procedure and submits revised packet

Owner-reported completion is 3/3; supported reviewer acceptance is 1/3. Reporting only the tracker’s “done” field would conceal both the missing compatibility evidence and the wrong test criterion.

A corrected procedure revision may also affect a readiness packet that cites the earlier version. Identify that dependency before closing the action, rather than treating each row as isolated administrative work.

Test the outcome, then check the decision

  1. Preserve the original concern and project closure criteria.
  2. Match evidence to the exact outcome, configuration and revision.
  3. Separate submitted, needs rework and accepted using the meanings in the project tracker.
  4. Check dependencies and record the authorized reviewer’s disposition, with its evidence locator.

Questions about this task

Does an uploaded file close an action?

Only when the file demonstrates the required outcome and the project’s authorized acceptance is recorded. Uploading minutes or a superseded procedure is not enough.

Sources and further reading

References inspected on 3 October 2026. The worked output is an authored example using the stated inputs.