Review a risk register for missing or weak risk statements

Use Arc Skills to review an existing risk register for vague statements, duplicated events and controls that do not address the cause. Get original wording beside proposed revisions, plus evidence-backed missing scenarios and owner actions.

Use this skill

Use Arc Skills to review these risk-register statements.

Inputs:
- Original register rows with IDs, owners and controls
- Objectives and current project evidence
- Approved risk definitions and scoring criteria, if available

Preserve each original row. Return its wording defect, a cause → event → consequence proposal, evidence basis, control gap and owner action. Separate issues and action items from future risks; identify duplicates without silently merging them.

Set up the toolkit · Read the skill instructions

What you provide and what you get

Inputs and outputs
What you haveHow it is usedWhat you get
Existing register rowsPreserve IDs and original wordingA row-by-row review
Project objectives and evidenceCheck the causal mechanism and omissionsSpecific revised or missing scenarios
Controls, owners and criteriaCheck actionabilityControl gaps and ownership decisions

“The supplier is late” is an issue, not a future event

Illustrative engineering example.

A three-row register mixes a vague future concern, an event that already happened and a requested activity.

R-01: “The sensor might fail.” Owner: electrical.
R-02: “The supplier delivery is late.” Planned date already passed; delivery absent.
R-03: “Do the EMC test.” No causal statement.
Project evidence: shielding unresolved; integration slot reserved; representative harness test not completed.
“The supplier is late” is an issue, not a future event
ID / original wordingReview findingProposed statement or classificationEvidence and next action
R-01: The sensor might fail.No cause, condition or project consequenceWith shielding unresolved, coupled noise may exceed sensor error limits and prevent required accuracy during powered operationConfirm routing and operating conditions; electrical owner addresses the noise mechanism
R-02: The supplier delivery is late.Existing issue; the event has happenedRecord delivery delay as an issue. Separate future risk: continued delay may prevent use of the reserved integration slotSupplier owner confirms recovery dates and slot decision criteria
R-03: Do the EMC test.Action item, not a risk statementRepresentative EMC evidence is absent; flight-harness coupling may require rework after integrationKeep the test as a mitigation action tied to the specific event and acceptance limit

The proposed R-01 and R-03 wording may describe the same physical event. Compare their configuration, consequence and authority before deciding whether to consolidate them; preserve both original IDs in the review.

A review can improve wording without rescoring the entire register. If likelihood and consequence definitions are missing, retain the uncertainty rather than assigning plausible-looking numbers.

Keep each original row beside the proposed correction

  1. Identify whether a row is a future risk, current issue, action or duplicate.
  2. Check cause, uncertain event and objective consequence against actual evidence.
  3. Compare controls and triggers with the causal mechanism and owner authority.
  4. Propose wording and missing scenarios with locators; leave merging, scoring and acceptance to the governing process.

Questions about this task

Do clearer risk statements automatically reduce risk?

No. They make the decision actionable. Exposure changes when a control is implemented and supported by evidence, or when the underlying situation changes.