Didero and Arc both merit evaluation for supplier sourcing, quote collection and open-PO follow-up. Arc connects those tasks to the selected BOM and drawing revision, with the buyer approving outbound requests and purchases. Compare the route from released drawing to supplier reply, authorised decision and purchasing-system readback. Compare AI procurement software for robotics teams.
Separate published workflow from observed execution
Arc publishes this comparison and sells one of the products evaluated here. The linked first-party sources were reviewed on 23 November 2026. This is a public-document comparison and a proposed evaluation, with no hands-on product trial, customer benchmark or measured outcome. Product editions, mailbox permissions, ERP versions, deployment region and commercial terms require confirmation for the intended setup.
Didero documents discovering suppliers, issuing RFQs with specifications and drawings, coordinating communication and normalising quote responses across units, currencies and terms. That published sourcing scope makes it worth evaluating for a buyer handling multiple replies. Didero sourcing and quoting.
Its PO page describes matching supplier acknowledgements against PO lines, routing quantity, price and delivery exceptions to a buyer, and writing confirmed lines, dates and status to an ERP. These are vendor-documented workflow assertions. The exact behaviour with your drawing revisions and ERP fields is still a demonstration question. Didero PO management.
Arc’s public robotics workflow connects BOM and drawing references with sourcing and supplier tracking. Arc can request quotes after buyer approval, compare bids and draft POs; after the buyer approves a final PO, it can record it in the configured ERP and send it to the supplier. Buyer approval also applies to messages and issued-order changes, and edited drafts return for approval. Confirm the connected systems and permissions for the intended setup. The fictional exception below was not run as a product trial.
Compare the decisions behind each automated step
| Decision | Didero evaluation | Arc evaluation |
|---|---|---|
| RFQ scope | Show the exact drawing attachment, line identity, quantity and need-by date issued to the approved suppliers | Show the selected BOM row, drawing revision and buyer-approved scope and recipient list before the request is sent |
| Quote comparison | Expose the source values and exceptions behind normalised units, costs and terms | Compare normalized unit and tooling charges, quote references, revision scope and unanswered conditions |
| Purchase authority | Demonstrate who approves the outbound contents and what the supplier receives | Show buyer approval of the final draft, then the configured ERP record and supplier send; edited drafts return for approval |
| Changed acknowledgement | Replay supplier counteroffer, buyer rejection or acceptance and the ERP result | Show proposed and accepted fields beside their source reply and affected build references |
| Technical change | Show how an offered Rev D routes to engineering before it changes the commercial commitment | Show the changed design reference and approved effectivity handed to the buyer |
| Failure and recovery | Retain stale replies, repeated messages and failed writes with an accountable owner | Demonstrate the same recovery evidence for any proposed tracking or external action |
Use the BOM RFQ template for the common input scope and the quote comparison guide for the calculation. A price normalisation should preserve the quoted source and any unresolved freight, tooling or inspection term.
Replay a 44-bracket award and changed promise
The fictional US warehouse robot run needs 20 robots. Its connector line uses two of the selected exact manufacturer MPN per robot, giving 40 connectors. BRK-101 Rev C needs two brackets per robot plus four spare brackets, giving 44. The need-by date is 12 December 2026 at the assembly site, with the required inspection evidence.
Two equivalent Rev C offers use the same drawing, finish and inspection scope. A quotes 44 at $24, $250 tooling and $45 freight, totalling $1,351 and all 44 usable by need-by. B requires an order of 50 at $19, $400 tooling and $70 freight, totalling $1,420 with only 20 usable by need-by. These are invented USD quotes covering only quoted units, tooling and freight. Confirm the omitted terms before purchasing.
The teaching award selects A on that quoted basis. Six compatible, accepted and unallocated brackets are then found in stock. After PO issue, A proposes 30 due 10 December and 14 due 16 December. The original PO remains 44 by 12 December until the accepted purchasing amendment says otherwise.
Copy a source-to-ERP decision timeline
Use this blank record to preserve what each actor proposed and accepted. Give each event a stable reference and date. Keep the message and exact attachment version available for readback.
| Event and source | Part, revision and quantity | Proposed or accepted state | Decision owner | Readback or open gap |
|---|---|---|---|---|
| Event | Source and scope | Decision state | Owner | Evidence to inspect |
|---|---|---|---|---|
| Quote award | A, BRK-101 Rev C, 44 for $1,351 | Approved offer basis, with omitted terms resolved before use | Buyer and required spend approver | Quote version and approved drawing package |
| Original PO issue | 44 Rev C usable by 12 December | Issued commitment retained | Buyer | Approved PO version and supplier transmission record |
| Supplier reply | 30 due 10 December, 14 due 16 December | Counteroffer awaiting buyer decision | Buyer with manufacturing input | Reply identity and matched PO line |
| Buyer accepts split | Two schedules totalling 44 | Approved revised commitment | Authorised buyer | Amendment, supplier readback and ERP schedules |
| Engineering proposes Rev D | Changed drawing and applicability under review | Technical proposal, with no assumed interchangeability | Engineering authority | Old and proposed drawings, affected units and review decision |
| Early receipt | 30 Rev C due 10 December | Incoming until checked and accepted | Receiving and quality | Actual lot, counted quantity, required reports and accepted quantity |
The filled timeline describes the proposed evaluation and its fictional decision states. It records no product execution. The supplier acknowledgement guide supplies the line-level reconciliation method.
If the buyer accepts the split and the timely 30 arrive and pass checks, bracket coverage is 6 + 30 = 36 usable by 12 December. The assembly needs 40, so it is four brackets short. Including the four spares, 44 − 36 = eight short. Before receipt, keep the 30 as committed incoming and the usable total conditional. The later 14 cannot cover that need-by date.
Test acceptance, rejection and revision routing
Replay both decisions on the changed date. In the rejection run, retain the supplier counteroffer and confirm the original order is still identifiable and awaiting a resolved commitment. In the acceptance run, inspect the two accepted schedules and their approval reference in the authoritative purchasing system. A copied reply should not create another order or duplicate supply.
Then introduce an acknowledgement naming Rev D. Ask engineering to approve or reject its applicability before the buyer changes the order. The open-PO revision change guide defines that technical-to-commercial handoff. A date approval gives no evidence that the revised bracket fits the selected build.
For each intended integration, record the exact ERP product and version, read and write fields, mailbox scope, permissions and failed-write behaviour. Ask who owns the correction when a message is matched to the wrong supplier alias or PO line. Vendor logos and a general integration statement leave those details to be verified.
Choose from the work you can verify
Didero is a fit to evaluate when quote communication and PO exception handling are the main purchasing workload. Arc is also a fit to evaluate for those tasks when the buyer needs them connected to the released build and its revision. Test each proposed setup’s approval and purchasing-system readback before relying on it.
Request a scoped commercial proposal covering the workflows, setup and integration work required. The $1,351 and $1,420 figures are fictional part quotes and contain no software price. Use the existing buyer-guide rubric for evaluation evidence and mandatory gates, applying the procurement criteria above. Retain unknowns and manual work beside observed results instead of assigning an unsupported product score.
Questions about Arc and Didero
Where does Didero’s documented PO workflow differ from Arc’s evidence here?
Didero’s public PO page describes acknowledgement matching, buyer-routed exceptions and ERP updates. Arc also matches supplier commitments to PO lines, prepares follow-up and records an approved PO in the configured ERP before it is sent. The buyer approves messages, purchases and issued-order changes. Neither description establishes a completed robotics replay in your setup.
Does accepting a split delivery approve a different bracket revision?
The buyer’s date decision accepts a commercial schedule within the reviewed scope. A different drawing revision needs engineering review of applicability and acceptance evidence, followed by the appropriate purchasing amendment. Retain the two decisions separately.
What should an ERP readback show after a supplier proposal is rejected?
It should identify the original approved order, retain the rejected supplier proposal and its decision, and show the unresolved follow-up. Confirm that the rejected dates and quantities have not become accepted schedules or usable supply.