Calculate the cost of a delayed robot build by comparing feasible wait, expedite and split routes over the same horizon, counting only the extra cash each route causes. Start with the dated material gap, paid idle hours and confirmed route fees, then keep common build work and sunk costs separate. Keep the schedule assumptions beside the costs so the buyer can see what would change the choice.
First establish when the material could be usable. The clear-to-build guide owns that calculation, and the shortage-disposition guide owns the allowed responses. This guide compares their incremental cost once scope, quantity and timing are understood.
Fix the horizon and payment rules
The fictional civilian R-P26 pilot assembles 12 warehouse robots at Austin site AUS-01. It needs 24 BRK-260 Rev B brackets. Six are accepted and reserved, and 18 remain on PO-P26-018. At the December 8, 2026 review, the supplier’s delayed standard route would make those 18 usable Friday December 18 at 09:00 CST, subject to acceptance. Other material, instructions and test capacity are assumed ready for each route.
Compare Monday December 14 at 09:00 through Wednesday December 30 at 17:00 CST. The assembly site has eight paid production hours per working day, Monday through Friday, and is closed Friday December 25. No other closure occurs in this horizon. Two hourly contractors are reserved from December 14, with a $60 rate per person-hour. The same build requires 96 productive person-hours in every option, or eight per robot.
The teaching contract requires eight paid reserved hours per contractor on each site working day while the allocated work is not ready. Those idle hours are billed in addition to the actual 96 productive hours needed to finish the build. They cannot be canceled or redeployed in this example. Contractors are released when the assigned build is complete, so no later idle reservation is billed. These are explicit fictional terms, not an industry contract assumption.
The 96 productive hours cost 96 × $60 = $5,760 in every route and are common to the comparison. The original bracket price, fixed employee salaries and a $600 fixture payment already made are also excluded from option differences. If a real contract charges the same fixed amount under every route, do not count the modeled idle hours as additional cash.
Compare routes that preserve acceptance and capacity
| Route | Material assumption | Assembly consequence within the fixed horizon |
|---|---|---|
| Wait | All 18 additional brackets usable Friday December 18 at 09:00 | 12 robots start December 18, 96 productive hours finish Monday December 28 at 17:00 |
| Expedite | Matching finish and inspection complete December 11, confirmed Saturday December 12 carrier collection, Monday December 14 dock at 09:00, Tuesday December 15 usable | 12 robots start December 15, 96 productive hours finish Tuesday December 22 at 17:00 |
| Split | Six accepted brackets permit three robots first, then the same standard 18-piece receipt becomes usable December 18 | First three start December 14, remaining nine start December 18, productive work finishes Thursday December 24 at 13:00 CST |
For the expedited route, the assumed weekend carrier operates on Saturday December 12 and confirms Monday dock arrival. Receiving needs one staffed working day after that dock event, so Monday arrival gives Tuesday usability. It does not cover Monday’s issue. No quality check is skipped. Those supplier, transport and inspection conditions remain proposals until the responsible owners accept them.
Oracle’s purchase-order scheduling guidance distinguishes ship, dock and postprocessing time and respects the relevant calendars. Use your actual route and receiving rules. A carrier offer that misses the dock cutoff can move usability even when its advertised transit time is unchanged.
For the split, six accepted brackets give 6 ÷ 2 = 3 robot sets. Those three use 3 × 8 = 24 productive person-hours, leaving nine robots and 72 productive hours after the later receipt. The NPI owner must approve the allocations, complete complementary kits and split instructions. The example assumes a separate available kit service charges a $300 restart fee without consuming additional assembly-contractor hours.
Reconcile extra paid hours before multiplying rates
| Route | Available reserved capacity before standard receipt | Productive use before that receipt | Extra paid idle hours |
|---|---|---|---|
| Wait | December 14–17: 4 days × 2 people × 8 hours = 64 | 0 | 64 |
| Expedite | December 14 only: 1 day × 2 people × 8 hours = 16 | 0 before Tuesday usability | 16 |
| Split | December 14–17: 64 person-hours | 24 hours building the first three robots | 64 − 24 = 40 |
The split uses both contractors for Monday’s 16 productive hours and Tuesday’s first eight person-hours. Its early 24 productive hours therefore finish Tuesday December 15 at 13:00 CST. The remaining Tuesday half-day plus Wednesday and Thursday contribute 8 + 16 + 16 = 40 idle person-hours. They are separate from the 72 productive hours after Friday’s receipt.
| Cost that changes | Wait | Expedite | Split |
|---|---|---|---|
| Extra paid idle hours | 64 × $60 = $3,840 | 16 × $60 = $960 | 40 × $60 = $2,400 |
| Additional route premium | 0 | Fictional expedite and freight offer: $1,400 | 0 |
| Additional receiving cost | 0 | Fictional added inspection coverage: $200 | 0 |
| Additional kit restart service | 0 | 0 | $300 |
| Incremental total | $3,840 | $2,560 | $2,700 |
Expedite is $1,280 below wait and $140 below split on these assumptions. If you want the total listed contractor and option cash, add the same $5,760 productive-build cost to each: $9,600 for wait, $8,320 for expedite and $8,460 for split. Adding that common amount changes no ranking. The original part price and other common spending remain outside those totals.
The figures are illustrative quotes and payment rules, not supplier performance or financial outcomes. No revenue, customer penalty, inventory write-off or fixed overhead reduction is included. Add such a cost only when its basis and route-specific timing are supported. Keep any noncash opportunity or customer impact separate from the incremental cash table.
Find the condition that changes the choice
incremental_wait = 64 × hourly_rate
incremental_expedite = 16 × hourly_rate + extra_route_premium + extra_receiving_cost
incremental_split = 40 × hourly_rate + extra_restart_fee
At $60 per person-hour:
total expedite extras at break-even with wait = (64 - 16) × 60 = $2,880
total expedite extras at break-even with split = (40 × 60 + 300) - 16 × 60 = $1,740
quoted expedite extras = 1,400 + 200 = $1,600
The next-best listed route is split, so $1,740 gives equal incremental cost for expedite and split. Total expedite extras below that amount make expedite cheaper. At $2,880 of extras, expedite and wait break even, and a lower amount makes expedite cheaper than wait. The teaching offer is only $140 below the split threshold. A later quote, extra handling fee or lost receiving day could reverse the ranking. At $40 per person-hour, wait costs $2,560, expedite $2,240 and split $1,900, so split becomes the least expensive listed route.
If all idle payments are unavoidable common spend or the team can be fully redeployed at no extra cash cost, set the incremental idle cost to zero. The listed differences then become $0 for wait, $1,600 for expedite and $300 for split. That narrow cash result does not decide customer value or technical risk. It shows why the payment and alternative-work assumptions must be explicit.
If an option crosses the comparison horizon with unfinished work, extend every option to the same later horizon or state the remaining obligation. Do not give an unfinished route a low cost by stopping its clock early. Here all three routes complete the same 96 productive person-hours before December 30 under the declared capacity and closure calendar.
Copy the decision record and approve the selected route
| Input or decision | Value and source | Owner |
|---|---|---|
| Build, part scope and dated gap | NPI and materials | |
| Comparison horizon and site calendars | Planner | |
| Paid reservation and cancellation terms | Buyer or contract owner | |
| Common productive work and excluded sunk spend | Operations and finance | |
| Extra idle hours per route | Operations | |
| Supplier, carrier and receiving extras | Buyer and receiving | |
| Approved split scope and setup work | NPI and quality | |
| Remaining technical or timing conditions | Engineering, quality and buyer | |
| Incremental total and break-even inputs | Finance reviewer | |
| Chosen route, approval and current commitment | Accountable decision owners |
ASQ’s supplier-selection guidance includes total supplier cost, delivery capability and incoming verification in the review. Use that broader evidence when deciding whether the mathematically cheaper route is feasible. Purchasing accepts the new commercial terms and schedule, quality preserves the acceptance scope, and the NPI owner approves capacity and allocations. Track the accepted route through the PO milestone record and recalculate when evidence changes.
Frequently asked questions
Should I count the whole company’s weekly payroll as the cost of a late part?
Count only costs that change because of the decision over the stated horizon. Fixed salaries and unavoidable common spend are excluded from this cash comparison. If lost engineering or assembly time prevents valuable alternative work, assess that opportunity separately with a supported assumption rather than calling all payroll saved cash.
When do idle contractor hours count as extra delay cost?
When the agreed contract makes those idle hours payable in addition to the productive hours needed for the same build, and the team cannot cancel or redeploy that reservation. If the payment is a fixed unavoidable total under every route, it is common spend and belongs outside the option difference.
Can the cheapest option be chosen before the supplier confirms its route?
Treat it as a scenario until the required finish, inspection, shipment, receiving date and fees are supported. Engineering and quality must accept any changed technical scope, the buyer accepts commercial and schedule changes, and the NPI owner confirms a feasible capacity and allocation plan.