Keep a second supplier ready by checking whether it can accept a specific approved order for the released part, quantity and usable date. Maintain its technical scope, current quote, accessible tooling, material, production slot, downstream processes and receipt plan. Give the buyer a last switch date and reconcile existing orders before moving demand.
Use three states. Discovered identifies a candidate. Qualified records accepted technical scope. Ready for this order adds current commercial, capacity and delivery evidence for the purchase.
Keep discovery and current readiness identifiable
NIST MEP's Supplier Scouting identifies US manufacturers with specified production and technical capabilities. It directs companies to an MEP Center for a search. A resulting candidate still needs your part-specific review and a current order decision.
Use the CNC qualification guide for technical acceptance. Use the low-volume supplier scorecard for actual delivery, document and quality evidence. Preserve the counts and scope behind that history when reviewing a larger order.
Price a recurring allocation against one demand
All shops, prices, approvals and events below are fictional teaching data for civilian indoor robots. The buyer needs 40 ea BRK-SR27 Rev B each month. The current build B-SR27-02 needs 40 at Austin on 26 February 2027 at 09.00 CST. It has zero accepted stock and no earlier orders covering this demand.
Primary P-01 in Ohio and secondary S-01 in Texas are qualified for this drawing, including the proposed 40-unit lot. Their separate approved finish processors are FP-01 and FS-01. Each holds its own buyer-owned fixture under documented possession and use rights. Both have the released manufacturing package and allocated material for 40.
Both replenish from approved aluminium mill M-01. Reserved material supports this order, while the register retains their shared exposure to future mill interruptions.
The fictional offers have a ten-unit minimum lot and multiples of ten. Unit prices include finish and the agreed supplier report. Setup, delivery and the buyer's added receipt-inspection cost below are fixed per ordered lot. USD is used throughout, with tax excluded by a common teaching assumption.
| Current-order cost | Primary, all 40 | Primary allocation, 30 | Secondary allocation, 10 |
|---|---|---|---|
| Unit price and parts | 40 × $22 = $880 | 30 × $22 = $660 | 10 × $26 = $260 |
| Setup | $60 | $60 | $80 |
| Freight to Austin | $40 | $40 | $50 |
| Added receipt inspection | $50 | $50 | $30 |
| Delivered and inspected total | $1,030 | $810 | $420 |
The planned 30/10 allocation totals $810 + $420 = $1,230, a $200 premium over all-primary sourcing. Its secondary order can supply performance evidence after receipt. The buyer approves this build's cost and capacity conditions.
Set an executable switch deadline
On 5 February, the buyer issues PO-SR27-S version 1 for ten to S-01. The primary's proposed 30 remains unissued pending capacity confirmation. S-01's written offer holds capacity for 40 total until 8 February at 16.00 CST, including its ordered ten. The listed costs include this option, with no separate reservation fee.
For 40, S-01 estimates two setup hours plus 40 × 0.20 = 8 machining hours, ten hours within a reserved twelve-hour slot. It confirms finish capacity, documents and dock arrival on 24 February. Receiving reserves 25 February for checks, supporting the 26 February issue if all required parts pass. The estimate and two-hour headroom are planning inputs, with actual output still pending.
The buyer's trigger is a missing primary commitment for timely usable supply by 8 February at 14.00 CST. This leaves two hours to approve the secondary amendment before its option expires. The long-lead alternatives guide owns the broader shortage response and existing-order disposition.
In the fictional event, P-01 cannot confirm the required schedule. The buyer verifies that its 30 were never authorised, approves the change and amends PO-SR27-S to version 2 for 40 at the unchanged secondary terms. S-01 acknowledges the full scope and 24 February dock date before the deadline.
| State after the switch | Quantity and cost |
|---|---|
| Primary production order for this demand | 0 |
| Current PO-SR27-S v2 | 40 ea, supersedes v1's ten |
| Secondary total | 40 × $26 + $80 + $50 + $30 = $1,200 |
| Increase over its original ten-unit order | $1,200 − $420 = $780 |
| Accepted at the 8 February snapshot | 0 |
| Planned usable on 26 February, subject to checks | 40 |
The amendment makes the supply obligation 40. It creates no additional ten-unit order. If the primary had already received an order, the buyer would first need its recorded cancellation, reduction or approved extra-stock disposition.
Copy the supplier-readiness record
Use one row for each shop and current demand. Keep the evidence behind the compact state.
| Readiness field | Value and evidence | Owner and expiry/next review |
|---|---|---|
| Supplier/site and discovered/qualified/order-ready state | ||
| Released part, quantity, build and usable date | ||
| Approved route, finish processor and technical limits | ||
| Quote, MOQ, total costs and validity | ||
| Fixture rights, physical access and manufacturing package | ||
| Allocated material and shared upstream dependencies | ||
| Capacity slot, completion, transport and receipt checks | ||
| Current orders and proposed transfer disposition | ||
| Switch trigger, deadline and purchasing approver | ||
| Actual accepted quantity and open quality actions | ||
| Change/requalification triggers and evidence review |
Review quote and capacity expiries separately from technical approval. This example's option expires on 8 February, while the team's next technical-evidence review is 1 March. A changed site, route, material, fixture or revision needs the applicable engineering and quality decision before another order. Reconfirm each monthly demand rather than copying this readiness state forward.
Frequently asked questions
Does qualification mean the second shop can take an order today?
Check current quantity, capacity, tooling access, material, terms and usable date against its approved scope. A historical qualification leaves those current-order questions open.
Must I split every order to keep a backup ready?
Choose the allocation from its cost, demand, evidence needs and agreed capacity service. The 30/10 proposal is one fictional choice, with a visible $200 premium. No universal share or readiness guarantee is implied.
How much can the secondary supply after the switch?
Here its held slot supports 40 total, including the existing ten. The amended 40-unit order replaces that ten-unit scope. Accepted supply remains zero until receiving and quality release the actual lot.