Qualify a new CNC supplier by checking the proposed manufacturing site, part-specific process and inspection capability, reserved capacity and representative sample evidence. Record which reviewers accept those inputs and limit the first production approval to a defined part, revision, route and lot. Use the resulting approval to define exactly which part, site and first lot the buyer can order.
Discovery gets a shop onto the shortlist. Qualification asks whether it can deliver your specific part. ASQ’s supplier-quality guidance recommends cross-functional selection involving purchasing, quality, engineering and production, and includes capacity, total cost and sample evaluation among the evidence to review. Use the supplier-discovery guide for finding candidates, then obtain their responses to your actual scope.
Separate three decisions before a production order
| Decision | What it permits | What it does not establish |
|---|---|---|
| Initial supplier clearance | The named company and site may take part in your approved sourcing or evaluation process | Technical acceptance of the part, award or usable stock |
| Technical sample acceptance | The stated sample evidence supports the agreed part and process decision | A stable production yield or acceptance of a later lot |
| Bounded production award | The buyer may order the approved scope under purchasing authority | Acceptance of parts before they arrive and pass receiving checks |
Your policy may call these stages by different names or combine reviews. Keep their evidence and limits visible. A supplier can be commercially cleared while the technical sample remains on hold. A sample can pass while the shop has no feasible production slot. An engineer’s fit check cannot replace the buyer’s expenditure approval.
Copy the supplier qualification checklist
| Question | Supplier evidence | Reviewer and decision |
|---|---|---|
| Which company and site will make the part? | Legal entity, manufacturing address and contact | Buyer verifies the intended supplier record |
| Does the quote acknowledge the released package? | Drawing, model, material, finish and explicit exceptions | Engineering reviews the selected scope |
| How will critical features be produced? | Operation route, workholding, program and process explanation | Manufacturing or engineering reviews feasibility |
| Who performs subcontracted finishing? | Named processor and controlled lot transfer | Quality reviews the required process evidence |
| Can measurements decide the drawing requirements? | Methods, gauges, calibration and suitable uncertainty treatment | Quality defines the acceptance plan |
| Which sample represents the production route? | Sample IDs, material lot, route, finish and reports | Engineering and quality accept or hold the stated sample |
| Is capacity reserved for the first lot? | Setup and cycle estimate, available slot, finish queue and ship plan | Buyer and NPI owner review the complete route |
| Which changes require another review? | Site, material, tooling, subcontractor, revision and quantity triggers | Owners record the approval boundary |
| What is cleared and what remains open? | Scope, evidence references and conditions | Buyer records the bounded first-order decision |
A five-axis machine is not evidence that the shop can measure a drawing’s position tolerance. Ask for the method, fixture and decision rule appropriate to the feature. If a shop subcontracts anodize, trace the part identity and agreed finish through that processor instead of reviewing machining alone.
Xometry’s US partner-onboarding page gives a concrete example of a network asking machining shops for GD&T experience and inspection equipment. Those are Xometry’s own eligibility conditions. They are useful questions to compare with your part, not universal requirements for a civilian robotics supplier.
Review a fictional backup supplier’s samples
This separate fictional qualification exercise uses R-P26’s BRK-260 Rev B warehouse-robot bracket. Supplier M is the incumbent with 18 additional brackets on the pilot’s current order. Candidate Supplier N proposes site N-01 with finishing at processor F-01. QUAL-N-003 and QUAL-N-006 below are evaluation lots retained for measurement and fit work. They contribute zero pilot-build stock.
Engineering supplies released drawing DW-BRK-260-B and quality plan QP-P26-B. Two illustrative features are a 12.00 mm locating boss with a ±0.05 mm limit and a 5.00 mm thickness with a ±0.10 mm limit. The plan also requires the drawing’s other characteristics and material/finish evidence. Suitable calibrated methods and the measurement decision rule are assumed for the teaching values below.
| Sample | Boss: 11.95–12.05 | Thickness: 4.90–5.10 | Review disposition |
|---|---|---|---|
| N-001, first set | 12.01 | 5.02 | Selected values pass, other required evidence reviewed |
| N-002, first set | 11.98 | 4.99 | Selected values pass, other required evidence reviewed |
| N-003, first set | 12.07 | 5.00 | Boss fails, technical production approval held |
| N-004, revised setup | 12.00 | 5.00 | Selected values pass under the revised route |
| N-005, revised setup | 11.99 | 5.01 | Selected values pass under the revised route |
| N-006, revised setup | 12.02 | 4.98 | Selected values pass under the revised route |
The first set has two of three samples within both shown limits. The reviewer records the failure and holds the production decision. Supplier N proposes a workholding correction under MFG-N-02, then produces the second three-piece set using that route and the required finish. Engineering and quality review the complete reports and accept those three samples for the bounded evaluation. The first failure remains in the record.
The second set’s three passing samples do not erase the first result or establish a production acceptance rate. Record the setup that was evaluated, how each sample relates to that setup and which evidence still depends on future production. Retain a decision that can be revisited if the site, fixture, finish processor or drawing changes.
Check the first lot’s capacity before award
| Input | Initial proposal | Revised proposal |
|---|---|---|
| Setup time | 2 machine hours | 2 machine hours |
| Cycle time for 18 parts | 18 × 0.25 hour = 4.5 machine hours | Same estimate, not a measured yield guarantee |
| Total machine slot needed | 2 + 4.5 = 6.5 hours | 6.5 hours |
| Reserved machine slot | 6 hours, 0.5-hour deficit | 7 hours, 0.5-hour headroom |
| Finish and inspection | Unconfirmed finish queue | Named finish slot and agreed inspection plan |
| Remaining risk | Insufficient slot and missing downstream date | Estimate sensitivity and actual production performance still need review |
An apparently small slot deficit is enough to hold a date promise. The revised seven-hour slot removes that specific arithmetic gap, but it does not prove the cycle estimate, scrap allowance or finish queue. Obtain the route and timing the supplier is actually committing to, including any bought-in input and downstream inspection. The custom-part milestone tracker records the progress evidence once the order exists.
supplier_id,legal_entity,manufacturing_site,part_id,drawing_revision,material,finish_processor,process_route,sample_lot,sample_report,measurement_plan,open_nonconformance,capacity_slot,first_lot_quantity,engineering_decision,quality_decision,buyer_clearance,award_conditions,requalification_triggers
Make the approval narrow enough to be useful
The teaching decision makes N-01 eligible for an initial production award of up to 18 BRK-260 Rev B brackets using route MFG-N-02 and finish processor F-01, subject to a current quote, a confirmed complete delivery route and buyer approval. It says nothing about another part, a different site or a 200-piece repeat lot. Receiving retains the later goods-acceptance decision.
Before awarding an order, reconcile R-P26’s six accepted brackets and Supplier M’s 18 open pieces. Passing Supplier N samples does not create new demand or cancel M’s order. A bridge or replacement purchase needs an explicit plan for overlapping supply and approved purchasing changes.
Use the incoming CNC inspection guide when the production lot arrives. Use the low-volume supplier scorecard for later delivery and quality evidence. Neither a retrospective score nor a generic supplier approval should conceal a changed route or unresolved technical sample.
Frequently asked questions
Does a supplier’s quality certificate qualify it to make my bracket?
A valid certificate can support the assessment within its stated scope. It does not establish that the named site can make your released features, control the finish route, inspect the part or reserve capacity for your lot. Review those questions and the required sample evidence before a bounded production approval.
How many qualification samples should I request?
Choose the quantity and checks from the part’s risk, process and intended decision with engineering and quality. The three-piece sets in this guide are invented teaching examples, not a prescribed sampling rule. A small passing set does not prove a stable production yield.
Can I order from the backup supplier as soon as its samples pass?
Sample acceptance is one input. Confirm supplier clearance, production route, capacity, commercial approval and net demand before award. In R-P26, Supplier M already has the 18-piece requirement on order, so a second 18-piece purchase would need a disposition for that existing supply and a new buyer decision.