A robotics BOM supply chain risk register should put the next buying decision beside the part it affects. Start with the selected revision, required quantity and material-issue date. Reconcile accepted stock and existing orders, then rank the unresolved actions by their decision deadlines and consequences for the build.
The result is an owned worklist across the BOM. One row might need an earlier supplier commitment. Another might need a lifecycle decision for a later batch. Give each an evidence reference, a due date and a condition for closing the action.
Start with the next build's usable-material requirement
Choose one approved build scope and a dated planning snapshot. Explode made assemblies into purchased inputs once. Aggregate a shared part across every branch that uses it. Keep an assembly bought complete at its purchasing boundary.
Use the MRP guide for the underlying demand and supply method. The risk register consumes that calculation and decides what needs attention first.
For each item, preserve the complete manufacturer part number or controlled drawing identity, selected revision, unit of measure and permitted build scope. A connector kit, loose contact and completed harness are different purchasing units. Convert packs to the selected unit explicitly before calculating coverage.
Use the date the material can be issued after receiving checks. Supplier dispatch, warehouse arrival and accepted material are separate events. Ask receiving and quality to confirm the time and evidence needed between them.
Keep each physical quantity and order line identifiable
Accepted stock available to this build excludes quarantine and reservations for other work. A reservation for this same build remains part of its coverage. Keep the stock lot, location and allocation reference beside the quantity.
Count the remaining quantity on each purchase-order line once. A quotation, supplier acknowledgement and in-transit update can all describe the same ordered units. An acknowledgement changes that line's commitment. When the lot arrives, reduce its open quantity as the received quantity enters the stock record.
For one issue date, use these calculations in the selected purchasing unit.
usable stock = accepted physical stock - reservations for other work
planned coverage = usable stock + eligible open quantities usable by issue
issue-date gap = max(0, demand - planned coverage)
eventual gap = max(0, demand - usable stock - all eligible existing open quantities)
Planned receipt coverage remains conditional on actual arrival and acceptance. Record its supplier commitment, required documents, receiving allowance and unresolved conditions. Keep an offered expedite or unapproved alternate in the action column until it becomes an accepted planning input.
The issue-date gap and eventual gap answer different questions. A late order can cover the total quantity while leaving the next build short. Buying the issue-date gap again would create excess if the existing late supply also arrives.
Work through a four-part civilian robot BOM
This fictional example covers twelve indoor inspection robots in batch B-2701, configuration CFG-P24 B. The snapshot is 5 January 2027 at 10.00 GMT. Material issue is 20 January at 09.00 GMT. Every identifier, quantity, supplier record, lifecycle flag and date below is invented teaching data.
Each robot needs one complete HR-P24 B harness, two ACT-P24 A actuators, four CK-P24 A connector kits and one CT-P24 C controller. Other build inputs and assembly capacity are outside this example. All stock and order quantities use the stated item unit.
| Item | Unit | Demand calculation | Accepted physical stock | Reserved for other work | Usable stock |
|---|---|---|---|---|---|
| HR-P24 B | complete harness | 12 × 1 = 12 | 4 | 0 | 4 |
| ACT-P24 A | actuator | 12 × 2 = 24 | 12 | 2 | 10 |
| CK-P24 A | connector kit | 12 × 4 = 48 | 44 | 8 | 36 |
| CT-P24 C | complete controller | 12 × 1 = 12 | 12 | 3 | 9 |
The controller location also holds two quarantined units. The connector location holds six quarantined kits. They are outside accepted physical stock and contribute zero usable quantity. Other-work reservations in the table are subtracted once.
The following remaining PO quantities are allocated to B-2701. Their fictional acknowledgements specify unchanged item scope. Receiving has reserved one staffed working day after each arrival for the required identity, document and functional checks.
| Unique PO line | Item | Remaining quantity | Warehouse arrival | Planned usable date | Counts at 20 January issue |
|---|---|---|---|---|---|
| PO-H21/1 | HR-P24 B | 8 harnesses | 21 January | 22 January | 0 |
| PO-A71/1 | ACT-P24 A | 8 actuators | 18 January | 19 January | 8 |
| PO-A72/1 | ACT-P24 A | 6 actuators | 25 January | 26 January | 0 |
| PO-K41/1 | CK-P24 A | 20 kits | 13 January | 14 January | 20 |
| PO-C31/1 | CT-P24 C | 3 controllers | 17 January | 18 January | 3 |
| Item | Planned issue-date coverage | Issue-date gap | Coverage after all existing orders | Eventual gap |
|---|---|---|---|---|
| HR-P24 B | 4 + 0 = 4 harnesses | 8 harnesses | 4 + 8 = 12 | 0 |
| ACT-P24 A | 10 + 8 = 18 actuators | 6 actuators | 10 + 8 + 6 = 24 | 0 |
| CK-P24 A | 36 + 20 = 56 kits | 0 | 56 | 0, with 8 kits beyond demand |
| CT-P24 C | 9 + 3 = 12 controllers | 0 | 12 | 0 |
At this snapshot, the purchasing problem is earlier usable supply for eight harnesses and six actuators. Both total quantities are already on hand or ordered. The register should first assess advancing those existing commitments or changing the permitted build scope.
If all listed delivery commitments remain in force and their planned receipt checks pass, four robots have harness coverage on 20 January. The eighteen timely actuators could serve nine robots. These limits overlap, so adding four and nine would double count robots. A material-complete allocation still requires every selected input and a separate assembly-readiness decision.
Rank actions by the last useful decision date
Use explicit priority classes tied to decisions. In this example, P1 means an uncovered next-build requirement with a response needed before issue. P2 means a future-batch, lifecycle or source-concentration action whose stated deadline still needs an owner. These are editorial worklist classes, with no probability score or universal weighting.
The chosen action deadlines below are fictional planning cutoffs. They allow the team to secure a receiving plan or authorise a build change. They are not measured supplier manufacturing times.
| Worklist order and priority | Risk and evidence at snapshot | Mitigation and decision owner | Deadline | Next review | Closure evidence |
|---|---|---|---|---|---|
| 1 · P1 | Eight HR-P24 B harnesses miss issue. ACK-H21-02, observed 5 January at 09.00 GMT, supports 22 January usable receipt. The current shop is approved for this drawing. A second shop remains unqualified. | Buyer requests an earlier commitment on PO-H21/1. If unresolved, the build lead reviews a four-robot split with receiving and engineering. | 6 January, 16.00 GMT | 6 January, 10.00 GMT | Accepted quantity/date and receiving plan, or an authorised split/hold identifying affected units. |
| 2 · P1 | Six ACT-P24 A actuators miss issue. ACK-A72-01, observed 5 January at 09.30 GMT, supports 26 January usable receipt. Two eligible sellers share the same manufacturer. | Buyer asks to advance PO-A72/1. A bridge purchase needs exact source eligibility and a recorded disposition for the original six units. | 8 January, 16.00 GMT | 6 January, 10.00 GMT | Revised acknowledged line and receipt plan, or an accepted sourcing/split decision with the old order reconciled. |
| 3 · P2 | CK-P24 A covers this batch. Fictional manufacturer notice LTB-K7, reviewed 5 January at 09.45 GMT, sets a 12 January last-order deadline. Later demand is unresolved. | Supply-chain owner validates future demand with engineering and finance, then decides on a bounded last-time buy or qualification programme. | 12 January, 12.00 GMT | 7 January, 10.00 GMT | Approved quantity and financial exposure, or an owned redesign/alternate plan that addresses the notice. |
| 4 · P2 | CT-P24 C has planned coverage but one qualified manufacturer. SOURCE-C3, reviewed 5 January at 09.50 GMT, contains no qualified replacement for the next batch. | Engineering identifies the replacement acceptance scope. Supply-chain owner checks lead time and capacity for the next dated demand. | 15 January, 16.00 GMT | 8 January, 10.00 GMT | Named qualification owner, evidence plan and next-batch coverage decision. |
Several sellers of the same manufacturer's part can help with buying routes while sharing an upstream exposure. Record seller eligibility and manufacturer concentration separately. A technically different part needs its own acceptance decision.
The supplier-change acceptance guide owns the technical evidence review. The long-lead alternatives guide owns the response to a selected shortage. Keep their detailed decisions linked from the register.
Attach lifecycle and source evidence to the exact row
Record the manufacturer's status wording and notice date. TI publishes categories including preview, active, not recommended for new designs, last time buy and obsolete. Use the policy for lifecycle status. Verify stock and receipt dates with the seller. TI product lifecycle policy
For catalogue supply, record the full orderable code, seller, territory, authorisation evidence and when stock or quotation data was observed. For made-to-drawing work, record the approved site, process, controlled drawing, test scope and remaining qualification conditions. Octopart's startup sourcing guide discusses authorised distributors, brokers, lifecycle checks and alternate planning. Apply those checks to the actual source offered. Startup component sourcing
Give evidence an expiry or next review suited to the decision. A manufacturer notice can remain relevant while a seller's stock observation becomes stale. After an acknowledgement changes, recalculate coverage and priorities from the same unique line reference.
Copy a register row for your next build
Keep the detailed stock and PO ledger behind each row. The compact register carries the resulting quantities, provenance and owned action. Add one row per unresolved item/build requirement. If a shared item affects several builds, link the allocation ledger so the same supply stays visible across them.
| Risk ID and build/item revision | Unit, demand and issue date | Usable stock | Unique PO refs, quantities and usable dates | Issue/eventual gaps | Evidence ref, observation time and conditions | Source qualification and lifecycle notice | Priority and mitigation | Decision owner | Deadline | Next review | Status and closure evidence |
|---|---|---|---|---|---|---|---|---|---|---|---|
Close a row when its chosen decision has evidence. A purchase order issued, an alternate suggested or a sample passing one test may leave the usable-date requirement unresolved. Preserve the remaining condition and next review.
Start with the earliest open decision for your next build. Use the RFQ template to obtain comparable scope, then the PO acknowledgement guide to record an accepted commitment.