Space funding and bids · Engineering evidence

C-LEO Funding: Preparing Call 2 and Call 3 Technical Proposals

Separate C-LEO Call 2 ARTES and Call 3 national routes, check the September 2026 application stages, and build an active-antenna evidence plan.

C-LEO means Connectivity in Low Earth Orbit. Its Call 2 ARTES route and Call 3 national route require different proposal processes. Checked 8 September 2026: Call 3 Stage One has closed; invited Stage Two applicants have a published deadline of 11 November 2026 at midday GMT. Existing Call 2 applicants should follow their separate UKSA and ESA checkpoints. C-LEO Call 3: national applicant guide C-LEO Call 2: ARTES applicant guide

Which C-LEO process applies?

Published route distinctions; check programme-issued instructions before submitting
QuestionCall 2: ARTESCall 3: national
Funding envelope£30 million in the UKSA callUp to £42 million
Next full-proposal datesIndicative UKSA checkpoint: 25 September 2026, midday (GMT) as written; ESA: 5 October 2026Stage Two: 11 November 2026, midday GMT, for invited applicants
Maturity emphasisStarting TRL 4–5, aiming at 7 or aboveTargets TRL 4–6, aiming at 7 or above; read the full eligibility conditions
Submission authorityUKSA national support process and ESA ARTES instructionsUKSA national application forms and associated annexes

The table summarises the two applicant guides, not a complete eligibility assessment. Call 2 labels its schedule indicative and uses “midday (GMT)” in September; do not silently convert that to UK summer time. Confirm the exact instruction through the programme before submission. For Call 3, check UK establishment, lead status, relevant technology, match funding, project dates and required forms in the national guide. Do not reuse the funding-rate assumptions of another call.

How do you connect the technical proposal to assessment?

Call 3’s Stage Two criteria give 20% each to strategic fit, value for money, catalysing investment, and innovation and technical feasibility; project management and benefits have 10% each. Technical feasibility asks for differentiation, approach, readiness progression and deliverables. Project management asks for milestones, risk, schedule, leadership and governance. Guidance Note E

Create an internal claim record for every major promise. Link the technical gap to the task that addresses it, the cost basis, the proposed evidence and the milestone decision. Then reconcile those records with the official application sections. The workbook is a preparation aid: submit only the documents and annexes permitted by the programme.

Worked example: an active-antenna evidence chain

Fictional preparation example; all values are proposed assumptions, not achieved results or UKSA requirements. A team proposes an antenna control assembly, revision B. Its bench prototype has exercised the command path, but thermal performance and representative host integration remain unverified. The intended output is a credible demonstration plan, not a self-awarded readiness level.

Fictional active-antenna package: proposed inputs and outputs
RecordProposed contentGap / accountable role
ANT-01 requirementCommanded beam state reached within 100 ms under the agreed interface and operating conditionsSystems lead must agree the timing boundary and conditions with the host.
Current evidenceIn the scenario, a revision A bench trace covers the command path onlyVerification lead must assess relevance to revision B; no environmental claim.
WP-2 planned workIntegrate revision B with a representative host simulator and execute the agreed timing testIntegration lead needs simulator access and the interface revision.
M-2 acceptance decisionReviewed test report, configuration list, raw trace references and anomaly dispositionTechnical authority decides whether the proposed criterion is met.
Industrialisation taskReview component availability and production test coverage for the intended designManufacturing lead owns the gap between demonstrator and repeatable product.

If the host changes its command protocol after the bench run, keep the original trace but reassess its applicability. A completed task does not make its evidence valid for a changed configuration. Use the change-impact guide to connect the affected requirement, firmware, procedure and milestone.

What should the final reconciliation check cover?

Compare the narrative, budget and schedule against the same work-package identifiers. Check that partner effort includes integration, review and corrective work, not just design hours. State which facilities and customer inputs are dependencies. Keep technical performance claims separate from commercial forecasts and show the basis of each forecast.

A systems lead should be able to follow one promise all the way to a planned result and owner. A bid lead should be able to explain why that work belongs in the relevant call and how it will be submitted. For supplier-specific scope, use the consortium handover checklist; for the distinction between current and target maturity, use the TRL evidence guide. Return to the UK funding route hub if the correct instrument is still unclear.

Try one work package in Arc

Arc connects requirements, interfaces, risks, verification activities and evidence in a programme model. Arc connected programme model Start with one bid commitment, its proposed evidence and the person responsible for the next decision. Engineers remain responsible for the technical judgement; using a tool does not establish eligibility, compliance or a funding award.

Frequently asked questions

Can I still submit a new C-LEO Call 3 Stage One bid?

The published Stage One deadline was 7 September 2026 at midday GMT. As checked on 8 September, that entry stage has closed. Stage Two is for invited applicants; possible supplier changes follow separate programme rules.

Are C-LEO Call 2 and Call 3 the same submission route?

No. Call 2 is an ARTES route involving UKSA support and ESA submission. Call 3 is a UK national grant call with its own forms, eligibility and timetable.

Does a successful test demonstrate the target TRL automatically?

No. Explain the technology, representative configuration, environment, critical functions and remaining limitations against the applicable readiness definition. A single result can leave major evidence gaps.

Evaluate Arc

Connect one bid commitment to its engineering evidence.

Try a work package in Arc: organise its requirements, interfaces, risks, verification work and evidence so your team can review the next decision.