Define entry and exit criteria for a test campaign

Arc Skills drafts Test Plan entry and exit criteria around the actual campaign article and objective. It returns a gate table that distinguishes readiness to execute from final requirement verification.

Use this skill

Use Arc Skills to define entry and exit criteria for the supplied test campaign.

Inputs:
- Campaign objective, Test Plan, requirement baseline, and article configuration
- Facility calibration, procedure approvals, and applicable safety prerequisites
- Planned Runs, anomaly process, and gate decision authority

Return entry and exit tables with objective evidence, owner, and current status.
Mark entry blocked when a required prerequisite is missing. Leave formal gate approval to the named authority

Set up the toolkit · Read the skill instructions

What you provide and what you get

Inputs and outputs
What you haveHow it is usedWhat you get
Campaign planDefines slots, article, and intended outcomeSpecific gates
Readiness recordsSupports safe, credible entryEntry decision
Runs and anomaly processDefines what completed execution meansExit decision and exceptions

Thermal-vacuum campaign gate review

Illustrative engineering example.

TV-1 uses article A-3 and chamber C-1. The article baseline is signed, but chamber calibration expires before the planned run; one open anomaly from a shakedown has no disposition.

TV-1: three thermal-vacuum runs on article A-3.
Article baseline AB-3: signed. Chamber C-1 calibration: expires before Run 1.
Procedure TP-3: approved. Shakedown anomaly AN-2: open.
Gate owner: test lead under the approved Test Plan.
Thermal-vacuum campaign gate review — illustrative output
GateObjective evidenceCurrent disposition
Entry: article and procedureAB-3 signed; TP-3 approvedMet for these two prerequisites.
Entry: calibrated chamber and hazard reviewC-1 calibration expires; hazard review [not supplied]Blocked until current record and required safety decision exist.
Exit: three runs and dataThree result packages with configuration and raw dataNot yet assessable before execution.
Exit: anomaliesAN-2 disposition and new anomaly logOpen; test lead decides whether it blocks run or close-out.

The campaign cannot enter on the supplied record because the chamber calibration will not be current at execution. The missing hazard review is shown as unknown rather than presumed failed if it is not a project prerequisite.

Exit does not require inventing a blanket “all tests pass” rule. It requires every planned slot to be executed or dispositioned and anomalies to be visible under the actual plan; a failed requirement may still leave a documented campaign close-out with an open verification action.

Tie each gate to a record

  1. Fix campaign objective, article baseline, planned Runs, and gate authority.
  2. List prerequisites that make execution safe and data credible.
  3. Define exit around result completeness, anomaly disposition, and handover state.
  4. Specify pause and re-entry evidence when interruption changes article or setup.

Questions about this task

Can the team waive calibration verbally?

Use the approved project process and decision authority. This example has no such record, so entry remains blocked.

Does campaign exit mean every requirement passed?

No. It means the campaign’s execution and exceptions are accounted for; requirement close-out is a separate disposition.